Construction of a basic-gate unit for the deep catastrophic sluice at the Nurek hydroelectric plant

  • Papers
  • Construction Projects of the Five-Year Period
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    Consideration of special conditions for the passage of flows through the sluice during the current year made it possible to employ a temporary scheme for maneuvering the basic gates and to complete construction of the sluice in time for the flood due to a reduction in the volume of construction-assembly work and a shortening of construction times.

  2. 2.

    The construction of supports for the underground working-gate unit in sectional reinforced concrete made it possible to reduce the time required for construction of the unit due to concurrent construction-assembly operations.

  3. 3.

    The adoption of reinforced-concrete support designs in combination with anchors enabled us to deviate from the traditional method employed to build similar units using reinforced-concrete arches.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature cited

  1. P. P. Listrovoi and N. A. Skvortsova, “The Nurek hydro project on the Vakhsh River,” Gidrotekh. Stroit., No. 1 (1960).

  2. V. F. Ilyushin, Underground Structures at the Nurek Hydroelectric Plant [in Russian], Informénergo, Moscow (1970).

    Google Scholar 

  3. G. A. Polonskii, “The development of gate building for hydraulic structures in the USSR,” Gidrotekh. Stroit., No. 6 (1968).

  4. L. A. Gusakova et al., “Improving the technology of mining-tunneling and concrete operations in the process of constructing underground structures for the first stage of the Nurek hydroelectric plant,” Energ. Stroit., No. 6 (1974).

  5. A. A. Podrechnev, “Improving construction technology for underground structures at the Nurek hydroelectric plant under complex geologic conditions,” in: A collection of material entitled “Mining and Blasting Operations in Hydraulic Construction” [in Russian], Tula (1973).

  6. Yu. K. Sevenard et al., “Passage of Vakhsh River flows during construction of the Nurek hydroelectric plant,” Gidrotekh. Stroit., No. 7 (1979).

Download references

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 6, pp. 9–12, June, 1980.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Gurtovnik, F.I., Shutenkov, S.V. & Mel'nikov, A.K. Construction of a basic-gate unit for the deep catastrophic sluice at the Nurek hydroelectric plant. Hydrotechnical Construction 14, 556–560 (1980). https://doi.org/10.1007/BF02305397

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02305397

Keywords

Navigation