Advertisement

Soil Mechanics and Foundation Engineering

, Volume 19, Issue 2, pp 39–42 | Cite as

Construction of reinforced-concrete scour localizing walls using the 1BA-15V drilling unit

  • N. V. Dmitriev
  • V. I. Mityaev
  • A. P. Tyurin
From The Experience Of Construction Organizations
  • 23 Downloads

Conclusion

1. Use of the 1BA-15V unit is expedient not only for building walls similar to the wall described here, but also for constructing deep foundations, chambers of great depth, and other underground structures of any shapes, with depths of not less than 5 m.

2. For a large working front and with good engineering preparation, it is possible to significantly increase the monthly output of the IBA-15V unit.

Keywords

Drilling Civil Engineer Great Depth Structural Foundation Hydraulic Engineer 
These keywords were added by machine and not by the authors. This process is experimental and the keywords may be updated as the learning algorithm improves.

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

Copyright information

© Plenum Publishing Corporation 1982