Tunnel conduit of the Papana reservoir

  • Papers
  • Five-Year Plan Projects
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    The use of a longitudinal dividing wall in the tunnel made it possible to dispense with construction of two independent tunnels for use in construction and operation and makes possible inspection and repair of equipment and construction of the conduit without interrupting its operation.

  2. 2.

    Construction of the surface spillway sill in the cofferdam between the bank and intake tower greatly reduces the volume of work on excavating an additional pit and improves operation of the hydrodevelopment.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 8, pp. 12–14, August, 1978.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Ilyushin, V.F., Krylova, S.N. Tunnel conduit of the Papana reservoir. Hydrotechnical Construction 12, 768–771 (1978). https://doi.org/10.1007/BF02304390

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02304390

Keywords

Navigation