Monolithizing the joints in pipelines during construction of the Zagorsk water storage power plant

  • Construction Organization and Technology
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    The stockholder firm “Gidrospetsstroi” first developed, made feasible, and completely mastered a new procedure for work involving the monolithizing of large-diameter steel-reinforced-concrete pipelines in the domestic practice of special operations. 978 butt joints between individual elements have been successfully grouted.

  2. 2.

    A procedure for monolithizing joints between reinforced-concrete elements in pipelines, which has been implemented in the construction of the Zagorsk water storage power plant, can be classified as a new technically complex form of special hydrotechnical operations. In conducting the work, it is necessary to focus attention on strict observance of the work procedure and on the possibility of bulging of the metallic lining of the conduit in the case where injection requirements are not observed. The work requires attending personnel with high qualifications, and should be accompanied by careful certification inspection to guarantee reliable quality of the work.

  3. 3.

    Operations involving the monolithizing of butt joints in the steel-reinforced-concrete pressure pipelines have important principal differences with respect to the classical grouting of joints in monolithizing concrete dams and with respect to work involving the grouting of massive reinforced-concrete blocks possessing elements of a work procedure involving filler grouting beyond the facing in individual cases.

  4. 4.

    The firm “Gidrospetsstroi,” which has significant experience in the design, technology, production, and quality control of special operations, guarantees their successful execution. The firm offers highly qualified specialists, production equipment, the timely publication of design-estimate documentation, and the realization of careful control (in the form of certification inspection) over the quality of their work.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature cited

  1. Temporary Instructions for Quality Control of Monolithized Joints in Sectional Elements of Pipelines Installed at the Zagorsk Water Storage Power Plant [in Russian], Gidroproekt, Moscow (1986).

Download references

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 8, pp. 11–15, August, 1992.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Dmitriev, N.V., Zhivoderov, V.N. & Chertykov, Y.D. Monolithizing the joints in pipelines during construction of the Zagorsk water storage power plant. Hydrotechnical Construction 26, 475–480 (1992). https://doi.org/10.1007/BF01544960

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF01544960

Keywords

Navigation