Conclusions
-
1.
The use of the watch method of organizing construction made it possible to stabilize the crew when constructing the structure and to provide normal rest conditions of the workers at a remote object.
-
2.
The collection of information materials considerably reduces labor expenditures of the engineers and technicians, control apparatus departments, and UPTK services when performing future and current planning and drawing up orders for construction materials and articles and work performance graphs, and permits conducting component-by-component checking of the course of the works.
-
3.
The collection of information materials creates the necessary conditions for solving problems of future and current preparation of works and provides quality of their performance.
Similar content being viewed by others
Additional information
Daugavagésstroi worked on the intake from August 1983 to March 1985.
Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 5, pp. 4–6, May, 1986.
Rights and permissions
About this article
Cite this article
Mekhed'kin, V.N. Organization of concreting at the water intake of the Kaisiadorys pumped-storage station. Hydrotechnical Construction 20, 258–260 (1986). https://doi.org/10.1007/BF01436014