Organization of concreting at the water intake of the Kaisiadorys pumped-storage station

  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    The use of the watch method of organizing construction made it possible to stabilize the crew when constructing the structure and to provide normal rest conditions of the workers at a remote object.

  2. 2.

    The collection of information materials considerably reduces labor expenditures of the engineers and technicians, control apparatus departments, and UPTK services when performing future and current planning and drawing up orders for construction materials and articles and work performance graphs, and permits conducting component-by-component checking of the course of the works.

  3. 3.

    The collection of information materials creates the necessary conditions for solving problems of future and current preparation of works and provides quality of their performance.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Authors

Additional information

Daugavagésstroi worked on the intake from August 1983 to March 1985.

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 5, pp. 4–6, May, 1986.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Mekhed'kin, V.N. Organization of concreting at the water intake of the Kaisiadorys pumped-storage station. Hydrotechnical Construction 20, 258–260 (1986). https://doi.org/10.1007/BF01436014

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF01436014

Keywords

Navigation