    On the basis of the experience in conducting the works and investigations it was established that it was expedient to construct the blanket in the upstream pool of the Baipaza hydrostation from loam of a local borrow pit in a mixture with gravel and pebbles hydraulically filled under water. The advantages of the given technology consist in the comparatively small labor intensity and cost of performing the hydraulic filling works and a high level of their mechanization.

  2. 2.

    Placing of a gravel-pebble mixture with loam promotes acceleration of the consolidation process and provides stability of the surface of the blanket.

  3. 3.

    It is recommended to check the quality of the hydraulically filled blanket and technology of performing the works with the use of a set of portable instruments for conducting investigations.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 9, pp. 19–21, September, 1989.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Efremov, N.A., Mukhamediev, V.N. & Shorin, S.L. Use of loams for hydraulic filling of the upstream blanket of the Baipaza hydroelectric station. Hydrotechnical Construction 23, 514–517 (1989). https://doi.org/10.1007/BF01432060

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF01432060

Keywords

Navigation