Adjustment and operation of the continuous concrete plant at the construction site of the Sayano-Shushenskoe hydroelectric station

  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    The continuous concrete plant constructed at the Sayano-Shushenskoe hydrostation has higher technicoeconomic indices and is more productive and reliable compared to cyclic plants.

  2. 2.

    Under conditions of large-scale construction of hydraulic structures the best technicoeconomic indices of concrete facilities can be provided by combining cyclic and continuous concrete plants with an optimal relationship of their capacities.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature cited

  1. N. A. Zinchenko and G. G. Ediger, “Operation of the proportioners of the concrete plant at the Krasnoyarsk hydroelectric station,” Stroit. Dorozh. Mash., No. 8 (1972).

  2. A. E. Bochkin et al., Concreting Works at the Construction Site of the Krasnoyarsk Hydroelectric Station [in Russian], Stroiizdat, Moscow (1977).

    Google Scholar 

Download references

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 4, pp. 14–17, April, 1981.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Zinchenko, N.A., Ryzhkov, V.A. & Gorbunov, Y.M. Adjustment and operation of the continuous concrete plant at the construction site of the Sayano-Shushenskoe hydroelectric station. Hydrotechnical Construction 15, 217–222 (1981). https://doi.org/10.1007/BF01429062

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF01429062

Keywords

Navigation