Existing schemes for constructing high concrete dams and ways to improve them

  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    Improvement of the existing cyclic methods of constructing concrete dams in recent years made it possible to considerably increase the rate of placing concrete and to reduce the specific labor expenditures on placing 1 m3 of concrete in the dam.

  2. 2.

    There are ways to improve further each of the existing methods of delivering concrete to the block. The most promising are the craneless layer-by-layer, cableway, and crane trestleless (stepwise) methods.

  3. 3.

    Further progress in concreting technology as a whole should develop in the direction of improving all concreting operations, especially those within the blocks.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature cited

  1. A. P. Aleksandrov and V. L. Kuperman, “Hydropower construction in the USSR on the occasion of the 60th anniversary of the October Revolution,” Gidrotekh. Stroit., No. 11 (1977).

  2. Yu. K. Kozyarskii, “Progressive solutions at the construction of the Ust-Ilim hydroelectric station,” Gidrotekh. Stroit., No. 9 (1978).

  3. I. N. Ivanov and A. P. Kurbatov, “Efficiency of water resources of the Angara-Enisei cascade,” Gidrotekh. Stroit., No. 5 (1978).

  4. A. V. Sklyarenko, “Formwork operations at the construction of the Chirkey hydroelectric stations,” Gidrotekh. Stroit., No. 5 (1975).

  5. A. S. Danilov et al., “Concreting operations at the construction of the arch dam of the Chirkey hydroelectric station,” Gidrotekh. Stroit., No. 10 (1975).

  6. V. V. Kon'ko and R. O. Godass, “Experience in concreting at the construction of the Zeya hydroelectric station,” Gidrotekh. Stroit., No. 12 (1973).

  7. S. I. Sadovskii and I. A. Zinchenko, “Improvement in the organization of operations at the construction of the Sayeno-Shushenskoe hydroelectric station,” Gidrotekh. Stroit., No. 2 (1979).

Download references

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 10, pp. 6–11, October, 1982.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Teleshev, V.I., Loshak, V.K. Existing schemes for constructing high concrete dams and ways to improve them. Hydrotechnical Construction 16, 527–533 (1982). https://doi.org/10.1007/BF01424308

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF01424308

Keywords

Navigation