Determination of optimal reserve contribution of thermal units to afford the wind power uncertainty

  • Mostafa EsmaeeliEmail author
  • Sajjad Golshannavaz
  • Pierluigi Siano
Original Research
  • 1 Downloads

Abstract

Due to unforeseen variations in wind speed profiles, wind farm integrations are recognized as intermittent and uncertain energy contributors. More specifically, integration of such renewable energy resources aligned with the conventional thermal units although reduces the emissions and brings about a clean environment, it introduces serious problems in assigning optimal and reliable level of these units in load supplying and spinning reserve provision. This situation is more intensified considering the uncertainties arisen by the power system loading demand. To facilitate such operational hurdles, the ongoing study puts forward an efficient model for assigning the optimal spinning reserve which accommodates the uncertainties in both the wind speed and load profiles. Stochastic behavior of these parameters is simulated by generating a proper number of scenarios through the Monte Carlo simulation (MCS) approach. Then, each of these scenarios is evaluated based on the established linear mixed integer approach in a deterministic fashion. Accordingly, a computationally efficient approach is obtained paving the way for real-world implementations and assuring the global optimum results. The proposed approach is applied to a 12-unit test system including 10 thermal units and 2 wind farms. Results are reflected in terms of the commitment status, energy dispatches, and reserve contributions of each committed unit. A comprehensive discussion is conducted to disclose the possible improvements.

Keywords

Wind farm integrations Wind speed and load uncertainties Stochastic analysis Mixed-integer linear programming Increased wind energy deployment Emission reduction. 

List of symbols

Sets and indices

\(g\)

Index of generating units.

\(t,T\)

Index and set of time intervals

\(s\)

Index of scenarios

\(d\)

Index of load points

\(w\)

Index of wind farms

Constants and parameters

\(P_{d}^{{}}\left( t \right)\)

Active power demand at load point d at time t

\({v_i}\left( t \right)\)

Wind speed at wind farm i at time t

\(A(g)\)

Coefficient of the piecewise linear production cost function of unit g

\({a_g},{b_g},{c_g}\)

Coefficients of the quadratic production cost function of unit g

\({\alpha _g},{\beta _g},{\gamma _g}\)

Coefficients of the quadratic emission function of unit g

\(f(l,g)\)

Slope of block l of the piecewise linear production cost function of unit g

\(NL\)

Number of segments in piecewise linearization approach

\(OFC\left( g \right)\)

Operation and maintenance fixed cost of thermal unit g

\(OFC\left( w \right)\)

Operation and maintenance fixed cost of wind farm w

\(OVC\left( g \right)\)

Operation and maintenance variable cost of thermal unit g

\(OVC\left( w \right)\)

Operation and maintenance variable cost of wind farm w

\(P_{G}^{{\hbox{max} }}\left( g \right)\)

Maximum power generating capacity of thermal unit g

\(P_{G}^{{\hbox{min} }}\left( g \right)\)

Minimum power generating limit of thermal unit g

\(P{r^S}\)

Probability of scenario s

\(RW\)

A fraction of total wind power considered as the reserve requirement due to wind power prediction errors

\({T_g}(l)\)

Upper limit in each segment of the linearized cost function of thermal unit g

\(n\left( t \right)\)

Number of hours at time interval t

Variables

\(P_{{GD}}^{S}\left( {g,t} \right)\)

Load contribution of thermal unit g at time t in scenario s

\(P_{{GR}}^{S}\left( {g,t} \right)\)

Reserve contribution of thermal unit g at time t in scenario s

\(P_{R}^{S}\left( t \right)\)

Fraction of total system load as the reserve requirement at time t in scenario s

\(P_{W}^{S}\left( {w,t} \right)\)

Generation of wind farm w at time t in scenario s

\({\rho ^S}\)

Probability of scenario s

\(u_{{i,t}}^{S}\)

Decision variables of unit i at time t in scenario s. (on = 1, off = 0)

\(x_{{i,t}}^{S}\)

State variables of unit i at time t in scenario s

\({\xi ^S}\)

Vector of scenario s

Notes

References

  1. Afkousi-Paqaleh M, Rashidinejad M, Pourakbari-Kasmaei M (2010) An implementation of harmony search algorithm to unit commitment problem. Electr Eng 92(6):215–225CrossRefGoogle Scholar
  2. Aien M, Hajebrahimi A, Fotuhi-Firuzabad M (2016) A comprehensive review on uncertainty modeling techniques in power system studies. Renew Sustain Energy Rev 57:1077–1089CrossRefGoogle Scholar
  3. Billinton R, Allan RN (1992) Reliability evaluation of engineering systems. Plenum press, New YorkCrossRefzbMATHGoogle Scholar
  4. Carrión M, Arroyo JM (2006) A computationally efficient mixed-integer linear formulation for the thermal unit commitment problem. IEEE Transactions on power systems 21(3):1371–1378CrossRefGoogle Scholar
  5. Dieu VN, Ongsakul W (2007) Improved merit order and augmented Lagrange Hopfield network for unit commitment. IET Gen Transm Distrib 1(4):548–556CrossRefGoogle Scholar
  6. Ghadimi N, Akbarimajd A, Shayeghi H, Abedinia O (2017) A new prediction model based on multi-block forecast engine in smart grid. J Ambient Intell Hum Comput 9(6):1873–1888CrossRefGoogle Scholar
  7. Handschin E, Slomski H (1990) Unit commitment in thermal power systems with long-term energy constraints. IEEE Trans Power Syst 5(4):1470–1477CrossRefGoogle Scholar
  8. Huang Y, Zheng QP, Wang J (2014) Two-stage stochastic unit commitment model including non-generation resources with conditional value-at-risk constraints. Electr Power Syst Res 116:427–438CrossRefGoogle Scholar
  9. Kazarlis SA, Bakirtzis AG, Petridis V (1996) A genetic algorithm solution to the unit commitment problem. IEEE Trans Power Syst 11(1):83–92CrossRefGoogle Scholar
  10. Kazemi M, Siano P, Sarno D, Goudarzi A (2016) Evaluating the impact of sub-hourly unit commitment method on spinning reserve in presence of intermittent generators. Energy 113:338–354CrossRefGoogle Scholar
  11. Kjeldsen NH, Chiarandini M (2012) Heuristic solutions to the long-term unit commitment problem with cogeneration plants. Comput Oper Res 39(2):269–282CrossRefzbMATHGoogle Scholar
  12. Kumar SS, Palanisamy V (2007) A dynamic programming based fast computation Hopfield neural network for unit commitment and economic dispatch. Electr Power Syst Res 77(8):917–925CrossRefGoogle Scholar
  13. Lange M (2005) On the uncertainty of wind power predictions—analysis of the forecast accuracy and statistical distribution of errors. Trans ASME-N-J Solar Energy Eng 127(2):177–184MathSciNetCrossRefGoogle Scholar
  14. Li T, Shahidehpour M (2005) Price-based unit commitment: A case of Lagrangian relaxation versus mixed integer programming. IEEE Trans Power Syst 20(4):2015–2025CrossRefGoogle Scholar
  15. Li X, Li T, Wei J, Wang G, Yeh WW (2014) Hydro unit commitment via mixed integer linear programming: a case study of the three gorges project, China. IEEE Trans Power Syst 29(3):1232–1241CrossRefGoogle Scholar
  16. Liang H, Tamang AK, Zhuang W, Shen XS (2014) Stochastic information management in smart grid. IEEE Commun Surveys Tutor 16(3):1746–1770CrossRefGoogle Scholar
  17. Liu G, Tomsovic K (2015) Robust unit commitment considering uncertain demand response. Electr Power Syst Res 119:126–137CrossRefGoogle Scholar
  18. Liu Z, Hajiali M, Torabi A, Ahmadi B, Simoes R (2018) Novel forecasting model based on improved wavelet transform, informative feature selection, and hybrid support vector machine on wind power forecasting. J Ambient Intell Hum Comput ‎9(6):1919–1931‎CrossRefGoogle Scholar
  19. Reddy SS, Bijwe PR, Abhyankar AR (2015) Joint energy and spinning reserve market clearing incorporating wind power and load forecast uncertainties. IEEE Syst J 9(1):152–164CrossRefGoogle Scholar
  20. Saber AY, Venayagamoorthy GK (2010) Intelligent unit commitment with vehicle-to-grid—a cost-emission optimization. J Power Sources 195(3):898–911CrossRefGoogle Scholar
  21. Saber AY, Venayagamoorthy GK (2012) Resource scheduling under uncertainty in a smart grid with renewables and plug-in vehicles. IEEE Syst J 6(1):103–109CrossRefGoogle Scholar
  22. Siahkali H, Vakilian M (2010) Stochastic unit commitment of wind farms integrated in power system. Electr Power Syst Res 80(9):1006–1017CrossRefGoogle Scholar
  23. Vieira B, Viana A, Matos M, Pedroso JP (2016) A multiple criteria utility-based approach for unit commitment with wind power and pumped storage hydro. Electr Power Syst Res 131:244–254CrossRefGoogle Scholar
  24. Yang Y, Wangb J, Guan X, Zhai Q (2012) Subhourly unit commitment with feasible energy delivery constraints. Appl Energy 96:245–252CrossRefGoogle Scholar
  25. Yu X, Zhang X (2014) Unit commitment using Lagrangian relaxation and particle swarm optimization. Int J Electr Power Energy Syst 61:510–522CrossRefGoogle Scholar
  26. Zhang J, Tang Q, Chen Y, Lin S (2016) A hybrid particle swarm optimization with small population size to solve the optimal short-term hydro-thermal unit commitment problem. Energy 109:765–780CrossRefGoogle Scholar
  27. Zou X, Li M, Wang W, Niu Y, Liu J (2015) Dispatch of wind-thermal power system containing heat storage units with fast ramping capabilities. In Power Tech IEEE 2015, Eindhoven, pp 1–6Google Scholar

Copyright information

© Springer-Verlag GmbH Germany, part of Springer Nature 2019

Authors and Affiliations

  1. 1.Faculty of Computer and Industrial EngineeringBirjand University of TechnologyBirjandIran
  2. 2.Electrical Engineering DepartmentUrmia UniversityUrmiaIran
  3. 3.Department of Management and Innovation SystemsUniversity of SalernoFiscianoItaly

Personalised recommendations