Optimal option selection for finishing works of high-rise building

  • Hyun-Soo Lee
  • San Roh
  • Moon-Seo Park
  • Han-Guk RyuEmail author
Construction Management

Abstract

Time-Cost Trade-Off Problem (TCTP), to determine optimal option among many options of construction work of high-rise building, is an issue that needs to be addressed to optimize construction duration with minimal cost. Despite the fact that the crashing process entailed in a network scheduling method is not suitable for the repetitive activities of a construction project, traditional time-cost trade-off focuses on the techniques for minimizing construction cost and time in a network-based scheduling method. In addition, time-cost relationships are usually presumed to be linear, not nonlinear. Since only integer durations (days) are considered in construction scheduling, linear approximation is not fully suitable to solve the TCTP. Thus, time-cost relationships need to be redefined at discrete points representing time-cost options. In addition, Tact scheduling is one of the most useful scheduling methods to reflect the repetitiveness usually demonstrated in a LOB (Line of Balance) form. However, Tact scheduling requires too much time and effort to determine Tact time, options (cost and time of activity), and the group of activities with the same option. Genetic Algorithms (GAs) are efficient in searching for optimal solutions among decision alternatives. Thus, the authors propose a time-cost trade-off method of Tact scheduling that uses GAs.

Keywords

schedule tact time-cost trade-off genetic algorithms optimization high-rise building 

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

References

  1. Arditi, D., Tokdemir, O. B., and Suh, K. (2002). “Challenges in line-of-balance scheduling.” J. of Construction Engineering and Management, ASCE, Vol. 128, No.1, pp. 545–556.CrossRefGoogle Scholar
  2. Feng, C., Liu, L., and Burns, S. A. (1997). “Using genetic algorithms to solve construction time-cost trade-off problems.” J. of Computing in Civil Engineering, ASCE, Vol. 11, No. 3, pp. 184–189.CrossRefGoogle Scholar
  3. Feng, C., Liu, L., and Burns, S. A. (2000). “Stochastic construction time-cost trade-off analysis.” J. of Computing in Civil Engineering, ASCE, Vol. 14, No. 2, pp. 117–126.CrossRefGoogle Scholar
  4. Hanna, A. S., Taylor, C. S., and Sullivan, K. T. (2005). “Impact of extended overtime on construction labor productivity.” J. of Construction Engineering and Management, ASCE, Vol. 131, No. 6, pp. 304–310.Google Scholar
  5. Li, H. and Love, P. (1997). “Using improved genetic algorithms to facilitate time-cost optimization.” J. of Construction Engineering and Management, ASCE, Vol. 123, No. 3, pp. 233–237.CrossRefGoogle Scholar
  6. Li, H., Cao, J.-N. and Love, P. E. D. (1999). “Using machine learning and GA to solver time-cost trade-off problems.” J. of Construction Engineering and Management, ASCE, Vol. 125, No. 5, pp. 347–353.CrossRefGoogle Scholar
  7. Liu, L., Burns, S. A., and Feng, C. (1995). “Construction time-cost trade-off analysis using LP/IP hybrid method.” J. of Construction Engineering and Management, ASCE, Vol. 121, No. 4, pp. 446–454.CrossRefGoogle Scholar
  8. Liu, J. and Rahbar, F. (2004). “Project time-cost trade-off optimization by maximal flow theory”. J. of Construction Engineering and Management, ASCE, Vol. 130, No. 4, pp. 607–609.CrossRefGoogle Scholar
  9. Suhail, S. A. and Neale, R. H. (1994). “CPM/LOB: New methodology to integrate CPM and line of balance.” J. of Construction Engineering and Management, ASCE, Vol. 120, No. 3, pp. 667–684.CrossRefGoogle Scholar
  10. Yamin, R. A. and Harmelink, D. J. (2001). “Comparison of Linear Scheduling Model (LSM) and Critical Path Method (CPM).” J. of Construction Engineering and Management, ASCE, Vol. 127, No. 5, pp. 374–381.CrossRefGoogle Scholar

Copyright information

© Korean Society of Civil Engineers and Springer-Verlag Berlin Heidelberg 2010

Authors and Affiliations

  • Hyun-Soo Lee
    • 1
  • San Roh
    • 2
  • Moon-Seo Park
    • 1
  • Han-Guk Ryu
    • 3
    Email author
  1. 1.Dept. of ArchitectureSeoul National UniversitySeoulKorea
  2. 2.IncheonKorea
  3. 3.Dept. of Architectural EngineeringChangwon National UniversityChangwonKorea

Personalised recommendations