Advertisement

Chinese Science Bulletin

, 54:4171 | Cite as

Shanghai Synchrotron Radiation Facility

  • MianHeng Jiang
  • Xiong Yang
  • HongJie Xu
  • ZhenTang Zhao
  • Hao Ding
Progress / High-Energy Physics

Abstract

The Shanghai Synchrotron Radiation Facility (SSRF) is an intermediate energy, third generation light source located in Zhangjiang High-Tech Park, Shanghai. In December 2007, an electron beam was first stored and accumulated in the SSRF storage ring. Since then the accelerator commissioning and beam line installation had steadily progressed toward routine user operation in May 2009. This article presents an overview of the SSRF design, construction, commissioning and current status of its user operation.

Keywords

synchrotron radiation light source SSRF construction commissioning 

References

  1. 1.
    Blewett J P. Synchrotron radition-Early history. J Synchrotron Rad, 1998, 5: 135–139CrossRefGoogle Scholar
  2. 2.
  3. 3.
    Chen S Y, Xu H J. Current status of the proposed Shanghai Synchrotron Radiation Facility. APAC98, Tsukuba, March 23–27, 1998Google Scholar
  4. 4.
    Chen S Y, Xu H J, Zhao Z T. The Shanghai Synchrotron Radiation Facility. PAC01, New York, March 29–April 2, 1999Google Scholar
  5. 5.
    Chen S Y, Xu H J, Zhao Z T. The SSRF accelerator complex. APAC01, Beijing, September 17–21, 2001Google Scholar
  6. 6.
    Zhao Z T, Xu H J, Ding H. The status of Shanghai Synchrotron Radiation Facility. Knoxville, May 16–20, 2005Google Scholar
  7. 7.
    Zhao Z T, Xu H J, Ding H. Construction of Shanghai Synchrotron Radiation Facility. APAC07, Indore, January 29–February 2, 2007Google Scholar
  8. 8.
    Xu H J, Zhao Z T. Current status and progresses of SSRF project. Nucl Sci Tech, 2008, 19: 1–6CrossRefGoogle Scholar
  9. 9.
    Zhao Z T, Xu H J, Ding H. Commissioning status of the Shanghai Synchrotron Radiation Facility. EPAC08, Genoa, June 23–27, 2008Google Scholar
  10. 10.
    Zhao M H, Lin G Q, Liu W H, et al. Commissioning of the 150 MeV SSRF Linac. EPAC08, Genoa, June 23–27, 2008Google Scholar
  11. 11.
    Li D M, Du H W, Li H H, et al. Status of the SSRF booster. EPAC08, Genoa, June 23–27, 2008Google Scholar
  12. 12.
    Li H H, Gu Q, Li D M, et al. Commissioning of the SSRF booster. EPAC08, Genoa, June 23–27, 2008Google Scholar
  13. 13.
    Dai Z M, Liu G M, Liu D K, et al. Status of SSRF storage ring. EPAC08, Genoa, June 23–27, 2008Google Scholar
  14. 14.
    Liu G M, Li H H, Zhang W Z, et al. Commissioning of the SSRF storage ring. EPAC08, Genoa, June 23–27, 2008Google Scholar
  15. 15.
    Zhao Z T, Xu H J, Ding H. Commissioning of Shanghai light source. PAC09, Vancouver, May 4–8, 2009Google Scholar

Copyright information

© Science in China Press and Springer Berlin Heidelberg 2009

Authors and Affiliations

  • MianHeng Jiang
    • 1
  • Xiong Yang
    • 2
  • HongJie Xu
    • 3
  • ZhenTang Zhao
    • 3
  • Hao Ding
    • 4
  1. 1.Chinese Academy of SciencesBeijingChina
  2. 2.Shanghai Municipal GovernmentShanghaiChina
  3. 3.Shanghai Institute of Applied PhysicsChinese Academy of SciencesShanghaiChina
  4. 4.Shanghai Urban Construction & CommunicationsShanghaiChina

Personalised recommendations