Deadline-based incentive contracts in project management with cost salience

  • Zhihua Chen
  • Yanfei LanEmail author
  • Ruiqing Zhao
  • Changjing Shang
Article
  • 83 Downloads

Abstract

The contractor’s procrastinating behavior owing to the psychology of cost salience exposes the project manager to the risk of time delay, which brings a significant challenge in project manager’s incentive contract design. This paper considers that a project manager pays a contractor over a menu of deadline-based incentive contracts to conduct a project which consists of two sequential tasks. The contractor is endowed with private cost salience information and unobservable efforts. The subjective assessments about the cost salience degree and the project variability are characterized as uncertain variables. Within the framework of uncertainty theory and principal-agent theory, we investigate the impacts of the existence of cost salience and information asymmetry on the incentive contract and the project manager’s profit. We confirm that cost salience can impel the project manager to lower both the fixed payment under full information and the penalty/incentive rate under pure moral hazard. Interestingly, we find that moral hazard can weaken the extent of inverse impact caused by the existence of cost salience for the project manager. Our study also shows that, for mitigating the adverse impacts brought by moral hazard, the project manager is more profitable to provide effort incentive when the contractor’s efforts are more productive or the project risk is in a higher level. Finally, other suggestions for mitigating the detrimental impacts brought by adverse selection are provided by numerical experiments.

Keywords

Uncertainty theory Incentive mechanism Project management Information asymmetry Cost salience 

Notes

Acknowledgements

This work was supported by the National Natural Science Foundation of China under Grant Nos. 71771166 and 71771165, Tianjin Natural Science Foundation under Grant No. 18JCQNJC04200, and partly by a S\({\hat{e}}\)r Cymru II COFUND Fellowship, UK.

References

  1. Akerlof, G. A. (1991). Procrastination and obedience. The American Economic Review, 81(2), 1–19.Google Scholar
  2. Ariely, D., & Wertenbroch, K. (2002). Procrastination, deadlines, and performance: Self-control by precommitment. Psychological Science, 13(3), 219–224.CrossRefGoogle Scholar
  3. Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357.CrossRefGoogle Scholar
  4. Boarnet, M. G. (1998). Business losses, transportation damage, and the northridge earthquake. Journal of Transportation and Statistics, 39, 49–63.Google Scholar
  5. Bubshait, A. A. (2003). Incentive/disincentive contracts and its effects on industrial projects. International Journal of Project Management, 21(1), 63–70.CrossRefGoogle Scholar
  6. Chen, T., Klastorin, T., & Wagner, M. R. (2015). Incentive contracts in serial stochastic projects. Manufacturing & Service Operations Management, 17(3), 290–301.CrossRefGoogle Scholar
  7. Chen, Z., Lan, Y., & Zhao, R. (2018). Impacts of risk attitude and outside option on compensation contracts under different information structures. Fuzzy Optimization and Decision Making, 17(1), 13–47.MathSciNetzbMATHCrossRefGoogle Scholar
  8. Dutta, S. (2008). Managerial expertise, private information, and pay-performance sensitivity. Management Science, 54(3), 429–442.CrossRefGoogle Scholar
  9. Ericson, K. M. (2017). On the interaction of memory and procrastination: Implications for reminders, deadlines, and empirical estimation. Journal of the European Economic Association, 15(3), 692–719.CrossRefGoogle Scholar
  10. Ferrari, J. R., & Roster, C. A. (2018). Delaying disposing: examining the relationship between procrastination and clutter across generations. Current Psychology, 37(2), 426–431.CrossRefGoogle Scholar
  11. Fu, Y., Chen, Z., & Lan, Y. (2018). The impacts of private risk aversion magnitude and moral hazard in R&D project under uncertain environment. Soft Computing, 22(16), 5231–5246.zbMATHCrossRefGoogle Scholar
  12. Gao, J., Yang, X., & Liu, D. (2016). Uncertain shapley value of coalitional game with application to supply chain alliance. Applied Soft Computing,.  https://doi.org/10.1016/j.asoc.2016.06.018.CrossRefGoogle Scholar
  13. Gibbons, R. (1987). Piece-rate incentive schemes. Journal of Labor Economics, 5(4), 413–429.CrossRefGoogle Scholar
  14. Kerkhove, L. P., & Vanhoucke, M. (2016). Incentive contract design for projects: The owner’s perspective. Omega, 62, 93–114.CrossRefGoogle Scholar
  15. Kwon, H. D., Lippman, S. A., & Tang, C. S. (2010). Optimal time-based and cost-based coordinated project contracts with unobservable work rates. International Journal of Production Economics, 126(2), 247–254.CrossRefGoogle Scholar
  16. Liu, B. (2007). Uncertainty Theory (2nd ed.). Berlin: Springer.zbMATHGoogle Scholar
  17. Liu, B. (2013). Extreme value theorems of uncertain process with application to insurance risk model. Soft Computing, 17(4), 549–556.zbMATHCrossRefGoogle Scholar
  18. Liu, Y., Chen, X., & Ralescu, D. A. (2015). Uncertain currency model and currency option pricing. International Journal of Intelligent Systems, 30(1), 40–51.CrossRefGoogle Scholar
  19. Mu, R., Lan, Y., & Tang, W. (2013). An uncertain contract model for rural migrant worker’s employment problems. Fuzzy Optimization and Decision Making, 12(1), 29–39.MathSciNetzbMATHCrossRefGoogle Scholar
  20. O’Donoghue, T., & Rabin, M. (1999). Incentives for procrastinators. The Quarterly Journal of Economics, 114(3), 769–816.zbMATHCrossRefGoogle Scholar
  21. Steel, P. (2007). The nature of procrastination: A meta-analytic and theoretical review of quintessential self-regulatory failure. Psychological Bulletin, 133(1), 65–94.MathSciNetCrossRefGoogle Scholar
  22. Tang, C. S., Zhang, K., & Zhou, S. X. (2015). Incentive contracts for managing a project with uncertain completion time. Production and Operations Management, 24(12), 1945–1954.CrossRefGoogle Scholar
  23. Walker, K. (2010). Prime Contractor Performance Report. Washington State Department of Transportation (WSDOT) Engineering and Regional Operations Division, Olympia, Washington.Google Scholar
  24. Wu, Y., Ramachandran, K., & Krishnan, V. (2014). Managing cost salience and procrastination in projects: Compensation and team composition. Production and Operations Management, 23(8), 1299–1311.CrossRefGoogle Scholar
  25. Xiao, W., & Xu, Y. (2012). The impact of royalty contract revision in a multistage strategic R&D alliance. Management Science, 58(12), 2251–2271.CrossRefGoogle Scholar
  26. Yang, K., Zhao, R., & Lan, Y. (2016). Incentive contract design in project management with serial tasks and uncertain completion times. Engineering Optimization, 48(4), 629–651.MathSciNetCrossRefGoogle Scholar
  27. Zhang, J. (2016). Deadlines in product development. Management Science, 62(11), 3310–3326.CrossRefGoogle Scholar
  28. Zhou, C., Peng, J., Liu, Z., & Dong, B. (2018). Optimal incentive contracts under loss aversion and inequity aversion. Fuzzy Optimization and Decision Making,.  https://doi.org/10.1007/s10700-018-9288-1.zbMATHCrossRefGoogle Scholar

Copyright information

© Springer Science+Business Media, LLC, part of Springer Nature 2019

Authors and Affiliations

  • Zhihua Chen
    • 1
  • Yanfei Lan
    • 1
    • 2
    Email author
  • Ruiqing Zhao
    • 1
  • Changjing Shang
    • 2
  1. 1.College of Management and EconomicsTianjin UniversityTianjinChina
  2. 2.Department of Computer ScienceAberystwyth UniversityAberystwythUK

Personalised recommendations