Hydrotechnical Construction

, Volume 29, Issue 10, pp 589–598 | Cite as

Incidents on structures of the Kolyma hydroelectric station during construction and temporary operation

  • Yu. I. Frishter
  • O. A. Kogodovskii
Organizational and Technological Construction
  • 15 Downloads

Conclusions

  1. 1.

    The temporary structures should have been designed with the same degree of reliability as that of the permanent structures.

     
  2. 2.

    Under the extreme and difficult conditions of construction in the Far North it is necessary to use only equipment proved by experience that can operate for a long time under all conditions without repair.

     
  3. 3.

    It was necessary to design the temporary outlet with consideration of permanent operation of the hydrostation.

     
  4. 4.

    It was necessary to make the transition from temporary to permanent operation controllable. It was advisable to provide for the possibility of discharging water during filling of the reservoir and thereby to regulate the level of the upper pool during filling. Furthermore, this outlet should serve for emptying the reservoir if necessary.

     

Keywords

Temporary Outlet Steel 09G2S Gantry Crane Hydro Development Groove Structure 
These keywords were added by machine and not by the authors. This process is experimental and the keywords may be updated as the learning algorithm improves.

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

Copyright information

© Plenum Publishing Corporation 1996

Authors and Affiliations

  • Yu. I. Frishter
  • O. A. Kogodovskii

There are no affiliations available

Personalised recommendations