Single-Machine Order Acceptance and Scheduling Problem Considering Setup Time and Release Date Relations

  • Research Article-Systems Engineering
  • Published:
Arabian Journal for Science and Engineering Aims and scope Submit manuscript

A Correction to this article was published on 28 May 2021

This article has been updated

Abstract

This paper focuses on a make-to-order production system, where rejection of some orders is inevitable due to limited production capacity. In such a system, accepting all orders may cause overloads, order delays, and customer dissatisfaction. For this reason, firms tend to reject some orders. The order acceptance and scheduling problem is defined as deciding simultaneously which orders to be selected and how to schedule these selected orders. An extension of this problem with sequence-dependent setup times and release dates has been rarely studied, and the existing studies suggest that setup activities wait for the release date to be performed. However, in real production environments this may not be the case. Therefore, this paper examines the relationships between setup times and release dates considering the overall scheduling literature. Previous scheduling studies define two different relationships concerning setup times and release dates. One of them considers setup time is completely dependent on release date, and the other one claims that they are completely independent. In this paper, a new relationship is addressed to propound that setup time may be partially dependent on the release date. The paper also proposes a new mixed integer linear programming formulation with O(n2) binary decision variables and O(n2) constraints. It includes a detailed computational analysis by solving available instances in the literature, which suggests that existing formulation can solve the test problems to optimality with up to 10 orders in a given time limit. Our proposed formulation, however, can solve the test problems to optimality with up to 50 orders within the same time limit. According to the findings, our approach seems to be more suitable for real-life applications, and the proposed formulation is extremely faster than the existing one.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5

Similar content being viewed by others

Change history

References

  1. Rom, W.O.; Slotnick, S.A.: Order acceptance using genetic algorithms. Comput. Oper. Res. 36, 1758–1767 (2009)

    MATH  Google Scholar 

  2. Slotnick, S.A.: Order acceptance and scheduling: a taxonomy and review. Eur. J. Oper. Res. 212, 1–11 (2011)

    MathSciNet  Google Scholar 

  3. Ostwald PF.: Cost estimating. In: Salvendy, G. (ed) Handbook of Industrial Engineering, 2nd edn, pp. 1263–1288 (1992)

  4. Allahverdi, A.; Ng, C.T.; Cheng, T.E.; Kovalyov, M.Y.: A survey of scheduling problems with setup times or costs. Eur. J. Oper. Res. 187(3), 985–1032 (2008)

    MathSciNet  MATH  Google Scholar 

  5. Allahverdi, A.; Gupta, J.N.; Aldowaisan, T.: A review of scheduling research involving setup considerations. Omega 27, 219–239 (1999)

    Google Scholar 

  6. Allahverdi, A.: The third comprehensive survey on scheduling problems with setup times/costs. Eur. J. Oper. Res. 246, 345–378 (2015)

    MathSciNet  MATH  Google Scholar 

  7. Schutten, J.M.; Leussink, R.A.M.: Parallel machine scheduling with release dates, due dates and family setup times. Int. J. Prod. Econ. 46, 119–125 (1996)

    Google Scholar 

  8. Thevenin, S.; Zufferey, N.; Widmer, M.: Order acceptance and scheduling with earliness and tardiness penalties. J. Heuristics 22, 849–890 (2016)

    Google Scholar 

  9. Oğuz, C.; Salman, F.S.; Bilgintürk Yalçın, Z.: Order acceptance and scheduling decisions in make-to-order systems. Int. J. Prod. Econ. 125, 200–211 (2010)

    Google Scholar 

  10. Cesaret, B.; Oğuz, C.; Salman, F.S.: A tabu search algorithm for order acceptance and scheduling. Comput. Oper. Res. 39, 1197–1205 (2012)

    Google Scholar 

  11. Chen, C.; Yang, Z.; Tan, Y.; He, R.: Diversity controlling genetic algorithm for order acceptance and scheduling problem. Math. Probl. Eng. 2014, 1–11 (2014)

    MATH  Google Scholar 

  12. Lin, S.W.; Ying, K.C.: Increasing the total net revenue for single machine order acceptance and scheduling problems using an artificial bee colony algorithm. J. Oper. Res. Soc. 64, 293–311 (2014)

    Google Scholar 

  13. Nguyen, S.; Zhang, M.; Johnston, M.; Tan, K.C.: Learning reusable initial solutions for multi-objective order acceptance and scheduling problems with genetic programming. In: European Conference on Genetic Programming, pp. 157–168. Springer, Berlin (2014)

  14. Nguyen, S.: A learning and optimizing system for order acceptance and scheduling. Int. J. Adv. Manuf. Technol. 86, 2021–2036 (2016)

    Google Scholar 

  15. Chaurasia, S.N.; Singh, A.: Hybrid evolutionary approaches for the single machine order acceptance and scheduling problem. Appl. Soft Comput. 52, 725–747 (2017)

    Google Scholar 

  16. Silva, Y.L.T.; Subramanian, A.; Pessoa, A.A.: Exact and heuristic algorithms for order acceptance and scheduling with sequence-dependent setup times. Comput. Oper. Res. 90, 142–160 (2018)

    MathSciNet  MATH  Google Scholar 

  17. Ghosh, J.B.: Job selection in heavily loaded shop. Comput. Oper. Res. 24, 141–145 (1997)

    MATH  Google Scholar 

  18. Nogueira, T.H.; Carvalho, C.R.V.D.; Ravetti, M.G.; Souza, M.C.D.: Analysis of mixed integer programming formulations for single machine scheduling problems with sequence dependent setup times and release dates. Pesquisa Operacional 39, 109–154 (2019)

    Google Scholar 

  19. Bianco, L.; Dell’Olmo, P.; Giordani, S.: Flow shop no-wait scheduling with sequence dependent setup times and release dates. INFOR 37, 3–19 (1999)

    Google Scholar 

  20. Liu, Z.; Cheng, T.C.E.: Minimizing total completion time subject to job release dates and preemption penalties. J. Sched. 7, 313–327 (2004)

    MathSciNet  MATH  Google Scholar 

  21. Nogueira, T.H.; Ramalhinho, H.L.; de Carvalho, C.R.; Ravetti, M.G.: A hybrid VNS-Lagrangean heuristic framework applied on single machine scheduling problem with sequence-dependent setup times, release dates and due dates. Optim. Lett. (2020). https://doi.org/10.1007/s11590-019-01525-7

  22. Qamhan, M.A.; Qamhan, A.A.; Al-Harkan, I.M.; Alotaibi, Y.A.: Mathematical modeling and discrete firefly algorithm to optimize scheduling problem with release date, sequence-dependent setup time, and periodic maintenance. Math. Probl. Eng. 1–16 (2019)

  23. Velez-Gallego, M.C.; Maya, J.; Montoya-Torres, J.R.: A beam search heuristic for scheduling a single machine with release dates and sequence dependent setup times to minimize the makespan. Comput. Oper. Res. 73, 132–140 (2016)

    MathSciNet  MATH  Google Scholar 

  24. Balakrishnan, N.; Kanet, J.J.; Sridharan, S.V.: Early/tardy scheduling with sequence dependent setups on uniform parallel machines. Comput. Oper. Res. 26, 127–141 (1999)

    MathSciNet  MATH  Google Scholar 

  25. Gharehgozli, A.H.; Tvakkoli-Moghaddam, R.; Zaerpour, N.: A fuzzy-mixed-integer goal programming model for a parallel-machine scheduling problem with sequence-dependent setup times and release dates. Robot. Comput. Integr. Manuf. 25, 853–859 (2009)

    Google Scholar 

  26. Lopes, M.J.P.; Carvalho, J.M.V.: A branch-and-price algorithm for scheduling parallel machines with sequence dependent setup times. Eur. J. Oper. Res. 176, 1508–1527 (2007)

    MathSciNet  MATH  Google Scholar 

  27. Manne, A.S.: On the job-shop scheduling problem. INFORMS 8, 219–223 (1959)

    MathSciNet  Google Scholar 

  28. Nessah, R.; Chu, C.; Yalaoui, F.: An exact method for Pm/sds, ri/∑ i = 1nCi problem. Comput. Oper. Res. 34, 2840–2848 (2007)

    MathSciNet  MATH  Google Scholar 

  29. Allahverdi, A.; Soroush, H.M.: The significance of reducing setup times/setup costs. Eur. J. Oper. Res. 187, 978–984 (2008)

    MATH  Google Scholar 

  30. Stern, H.I.; Avivi, Z.: The selection and scheduling of textile orders. Eur. J. Oper. Res. 44, 11–16 (1990)

    MATH  Google Scholar 

  31. Slotnick, S.A.; Morton, T.E.: Order acceptance with weighted tardiness. Comput. Oper. Res. 34, 3029–3042 (2007)

    MATH  Google Scholar 

  32. Keskinocak, P.; Ravi, R.; Tayur, S.: Algorithms for reliable lead time quotation. GSIA Working Paper. Carnegie Mellon University, Pittsburgh, PA (1997)

  33. Keskinocak, P.; Ravi, R.; Tayur, S.: Scheduling and reliable lead-time quotation for orders with availability intervals and lead-time sensitive revenues. Manag. Sci. 47, 264–279 (2001)

    MATH  Google Scholar 

  34. Lewis, H.F.; Slotnick, S.A.: Multi-period job selection: planning work loads to maximize profit. Comput. Oper. Res. 29, 1081–1098 (2002)

    MATH  Google Scholar 

  35. Charnsirisakskul, K.; Griffin, P.M.; Keskinocak, P.: Order selection and scheduling with leadtime flexibility. IIE Trans. 36, 697–707 (2004)

    MATH  Google Scholar 

  36. Charnsirisakskul, K.; Griffin, P.M.; Keskinocak, P.: Pricing and scheduling decisions with leadtime flexibility. Eur. J. Oper. Res. 171, 153–169 (2006)

    MathSciNet  MATH  Google Scholar 

  37. Slotnick, S.A.; Morton, T.E.: Selecting jobs for a heavily loaded shop with lateness penalties. Comput. Oper. Res. 23, 131–140 (1996)

    MATH  Google Scholar 

  38. Yang, B.; Geunes, J.: A single resource scheduling problem with job-selection flexibility, tardiness costs and controllable processing times. Comput. Ind. Eng. 53, 420–432 (2007)

    Google Scholar 

  39. Nobibon, F.T.; Leus, R.: Exact algorithms for a generalization of the order acceptance and scheduling problem in a single-machine environment. Comput. Oper. Res. 38, 367–378 (2011)

    MathSciNet  MATH  Google Scholar 

  40. Reisi-Nafchi, M.; Moslehi, G.: A hybrid genetic and linear programming algorithm for two-agent order acceptance and scheduling problem. Appl. Soft Comput. 33, 37–47 (2015)

    Google Scholar 

  41. Wang, X.; Zhu, Q.; Cheng, T.C.E.: Subcontracting price schemes for order acceptance and scheduling. Omega 54, 1–10 (2015)

    Google Scholar 

  42. Hosteins, P.; Cordone, R.; Righini, G.: The prize-collecting scheduling problem with deadlines. Electron. Not. Discrete Math. 55, 57–60 (2016)

    MATH  Google Scholar 

  43. Garcia, C.: Resource-constrained scheduling with hard due windows and rejection penalties. Eng. Optim. 48, 1515–1528 (2016)

    MathSciNet  Google Scholar 

  44. Trigos, F.; López, E.M.: Maximising profit for multiple-product, single-period, single-machine manufacturing under sequential set-up constraints that depend on lot size. Int. J. Prod. Res. 54, 1134–1151 (2016)

    Google Scholar 

  45. Xie, X.; Wang, X.: An enhanced ABC algorithm for single machine order acceptance and scheduling with class setups. Appl. Soft Comput. 44, 255–266 (2016)

    MathSciNet  Google Scholar 

  46. Zandieh, M.; Roumani, M.: A biogeography-based optimization algorithm for order acceptance and scheduling. J. Ind. Prod. Eng. 34, 312–321 (2017)

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Papatya S. Bıçakcı.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Bıçakcı, P.S., Kara, İ. & Sağır, M. Single-Machine Order Acceptance and Scheduling Problem Considering Setup Time and Release Date Relations. Arab J Sci Eng 46, 1549–1559 (2021). https://doi.org/10.1007/s13369-020-04759-1

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s13369-020-04759-1

Keywords

Navigation