A vendor–buyer integrated inventory system with variable lead time and uncertain market demand

  • Original Paper
  • Published:
Operational Research Aims and scope Submit manuscript

Abstract

In this paper, we consider a single-vendor single-buyer integrated inventory model in which the replenishment lead time is assumed to be a linear function of batch size, setup time, and transportation time. Both the vendor and the buyer are interested to invest in reducing the ordering cost. Shortages, if occur in buyer’s inventory, are partially backlogged with a certain limit of backorder price discount. The objective of the study is to derive the optimal decisions and the best investment policy by minimizing the expected annual total cost of the integrated system. The existence and uniqueness of the optimal solution are investigated and an efficient algorithm is designed to find the optimal solution of the proposed model numerically. We demonstrate the aids of reducing order-processing cost through numerical examples and show that it has significant effect on lot sizing decisions. It is also observed that transportation delay forces the buyer to stock more in order to defend the stock-out situation.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4

Similar content being viewed by others

References

  • Affisco JF, Paknejad MJ, Nasri F (2002) Quality improvement and setup reduction in the joint economic lot size model. Eur J Oper Res 142:497–508

    Google Scholar 

  • Annadurai K, Uthayakumar R (2010) Controlling setup cost in (Q, r, L) inventory model with defective items. Appl Math Model 34:1418–1427

    Google Scholar 

  • Arkan A, Hejazi SR (2012) Coordinating orders in a two echelon supply chain with controllable lead time and ordering cost using the credit period. Comp Ind Eng 62:56–69

    Google Scholar 

  • Aslani A, Taleizadeh AA, Zanoni S (2017) An EOQ model with partial backordering with regard to random yield: two strategies to improve mean and variance of the yield. Comp Ind Eng 112:379–390

    Google Scholar 

  • Banerjee A (1986) A joint economic-lot-size model for purchaser and vendor. Decis Sci 17:292–311

    Google Scholar 

  • Ben-Daya M, Hariga M (2004) Integrated single vendor single buyer model with stochastic demand and variable lead-time. Int J Prod Econ 92:75–80

    Google Scholar 

  • Ben-Daya M, Raouf A (1994) Inventory models involving lead time as a decision variable. J Oper Res Soc 45:579–582

    Google Scholar 

  • Braglia M, Castellano D, Gallo M (2016) An approximated closed form minimum-cost solution to the (r, q) policy with complete backordering and further developments. Appl Math Model 40:8406–8423

    Google Scholar 

  • Càrdenas-Barròn LE, Chung K-J, Kazemi N, Shekarian E (2018) Optimal inventory system with two backlog costs in response to a discount offer: corrections and complements. Oper Res Int J 18(1):97–104

    Google Scholar 

  • Cetinkaya S, Lee C, Tekin E (2008) A stochastic model for joint inventory and outbound shipment decisions. IIE Trans 40:324–340

    Google Scholar 

  • Chaharsooghi SK, Heydari J (2010) Supply chain coordination for the joint determination of order quantity and reorder point using credit option. Eur J Oper Res 204:86–95

    Google Scholar 

  • Chang HC, Ouyang LY, Wu KS, Ho CH (2006) Integrated vendor–buyer cooperative inventory models with controllable lead-time and ordering cost reduction. Eur J Oper Res 170:481–495

    Google Scholar 

  • Chen F (1998) Echelon reorder points, installation reorder points, and the value of centralized demand information. Manag Sci 44(12):S221–S234

    Google Scholar 

  • Coates ER, Sarker BR, Ray TG (1996) Manufacturing setup cost reduction. Comput Ind Eng 31:111–114

    Google Scholar 

  • Chuang BR, Ouyang LY, Chung KW (2004) A note on periodic review inventory model with controllable setup cost and lead time. Comput Oper Res 31:549–561

    Google Scholar 

  • Das C (1975) Effect of lead time on inventory: a static analysis. Oper Res Quar 26:273–282

    Google Scholar 

  • Das K (2018) Integrating lean systems in the design of a sustainable supply chain model. Int J Prod Econ 198:177–190

    Google Scholar 

  • Dey O, Giri BC (2014) Optimal vendor investment for reducing defect rate in a vendor-buyer integrated system with imperfect production process. Int J Prod Econ 155:222–228

    Google Scholar 

  • Foote B, Kebriaei N, Kumin H (1988) Heuristic policies for inventory ordering problems with long and randomly varying lead times. J Oper Manag 7:115–124

    Google Scholar 

  • Glock CH (2012) Lead time reduction strategies in a single-vendor-single-buyer integrated inventory model with lot size-dependent lead times and stochastic demand. Int J Prod Econ 136:37–44

    Google Scholar 

  • Goyal SK (1976) An integrated inventory model for a single supplier-single customer problem. Int J Prod Res 15:107–111

    Google Scholar 

  • Goyal SK (1988) A joint economic-lot-size model for purchaser and vendor: a comment. Decis Sci 19:236–241

    Google Scholar 

  • Ha D, Kim SL (1997) Implementation of JIT purchasing: an integrated approach. Prod Plan Cont l8:152–157

    Google Scholar 

  • Ho W-T, Hsiao Y-C (2012) Single supplier single retailer inventory model controlled by the reorder and shipping points with sharing information. Int J Syst Sci 43(4):673–681

    Google Scholar 

  • Heydari J, Zaabi-Ahmadi P, Choi TM (2016) Coordinating supply chains with stochastic demand by crashing lead times. Comput Oper Res. https://doi.org/10.1016/j.cor.2016.10.009

    Article  Google Scholar 

  • Hossain SJ, Ohaiba MM, Sarker BR (2017) An optimal vendor-buyer cooperative policy under generalized lead-time distribution with penalty cost for delivery lateness. Int J Prod Econ 188:50–62

    Google Scholar 

  • Hsiao YC (2008) A note on integrated single vendor single buyer model with stochastic demand and variable lead time. Int J Prod Econ 114:294–297

    Google Scholar 

  • Huang C-K (2010) An integrated inventory model under conditions of order processing cost reduction and permissible delay in payments. Appl Math Model 34:1352–1359

    Google Scholar 

  • Huang C-K, Tsai D-M, Wu J-C, Chung K-J (2010) An integrated vendorbuyer inventory model with order-processing cost reduction and permissible delay in payments. Eur J Oper Res 202:473–478

    Google Scholar 

  • Jha JK, Shanker K (2013) Single-vendor multi-buyer integrated production-inventory model with controllable lead time and service level constraints. Appl Math Model 37:1753–1767

    Google Scholar 

  • Kang JH, Kim YD (2010) Inventory replenishment and delivery planning in a two-level supply chain with compound Poisson demands. Int J Adv Manuf Tech 49:1107–1118

    Google Scholar 

  • Karmarker US (1987) Lot sizes, lead times and in-process inventories. Manag Sci 33:409–418

    Google Scholar 

  • Kazemi N, Shekarian E, Càrdenas-Barròn LE, Olugu EU (2015) Incorporating human learning into a fuzzy EOQ inventory model with backorders. Comput Ind Eng 87:540–542

    Google Scholar 

  • Kazemi N, Abdul-Rashid SH, Shekarian E, Bottani E, Montanari R (2016) A fuzzy lot-sizing problem with two-stage composite human learning. Int J Prod Res 54(16):5010–5025

    Google Scholar 

  • Keller G, Noori H (1988) Justifying new technology acquisition through its impact on the cost of running an inventory policy. IIE Trans 20:284–291

    Google Scholar 

  • Kim JS, Benton WC (1995) Lot size dependent lead times in a Q, R inventory system. Int J Prod Res 33:41–58

    Google Scholar 

  • Kim KL, Hayya JC, Hong JD (1992) Setup reduction in economic production quantity model. Decis Sci 23:500–508

    Google Scholar 

  • Kurdhi NA, Prasetyo J, Handajani S (2015) An inventory model involving back-order price discount when the amount received is uncertain. Int J Syst Sci 47:662–671

    Google Scholar 

  • Lee WC, Wu JW, Hsu JW (2006) Computational algorithm for inventory model with a service level constraint lead time demand with the mixture of distributions and controllable negative exponential backorder rate. Appl Math Comp 175:1125–1138

    Google Scholar 

  • Liao CJ, Shyu CH (1991) An analytical determination of lead time with normal demand. Int J Oper Prod Manag 11:72–78

    Google Scholar 

  • Li Y, Xu X, Ye F (2011) Supply chain coordination model with controllable lead time and service level constraint. Comput Ind Eng 61:858–864

    Google Scholar 

  • Lin Y-J (2008) Minimax distribution free procedure with backorder price discount. Int J Prod Econ 111(1):118–128

    Google Scholar 

  • Lin YJ (2010) A stochastic periodic review integrated inventory model involving defective items, backorder price discount, and variable lead time. 4OR Q J Oper Res 8:281–297

    Google Scholar 

  • Lou K-R, Wang W-C (2013) A comprehensive extension of an integrated inventory model with ordering cost reduction and permissible delay in payments. Appl Math Model 37:4709–4716

    Google Scholar 

  • Magson D (1979) Stock control when the lead time cannot be considered constant. J Oper Res Soci 30:317–322

    Google Scholar 

  • Mandal P, Giri BC (2015) A single-vendor multi-buyer integrated model with controllable lead time and quality improvement through reduction in defective items. Int J Syst Sci Oper Logi 2:1–14

    Google Scholar 

  • Montgomery DC, Bazaraa MS, Keswani AK (1973) Inventory models with a mixture of backorders and lost sales. Nav Res Logi Quart 20:255–263

    Google Scholar 

  • Naddor E (1966) Inventory systems. Wiley, New York

    Google Scholar 

  • Nasri F, Affisco JF, Paknejad MJ (1990) Setup cost reduction in an inventory model with finite-range stochastic lead-times. Int J Prod Res 28:199–212

    Google Scholar 

  • Nematollahi M, Hosseini-Motlagh S-M, Heydari J (2017) Coordination of social responsibility and order quantity in a two-echelon supply chain: a collaborative decision-making perspective. Int J Prod Econ 184:107–121

    Google Scholar 

  • Nouri M, Hosseini-Motlagh S-M, Nematollahi M, Sarker BR (2018) Coordinating manufacturer’s innovation and retailer’s promotion and replenishment using a compensation-based wholesale price contract. Int J Prod Econ 198:11–24

    Google Scholar 

  • Ouyang LY, Chuang BR (2001) Mixture of inventory model involving variable lead time and controllable backorder rate. Comput Ind Eng 40:339–348

    Google Scholar 

  • Ouyang LY, Yeh NC, Wu KS (1996) Mixture inventory model with backorders and lost sales for variable lead time. J Oper Res Soci 47:829–832

    Google Scholar 

  • Ouyang LY, Wu KS, Ho CH (2004) Integrated vendor–buyer cooperative models with stochastic demand in controllable lead time. Int J Prod Econ 92:255–266

    Google Scholar 

  • Ouyang LY, Wu KS, Ho CH (2007) An integrated vendorbuyer inventory model with quality improvement and lead time reduction. Int J Prod Econ 108:349–358

    Google Scholar 

  • Pan CH, Hsiao YC (2001) Inventory models with back-order discounts and variable lead time. Int J Syst Sci 32:925–929

    Google Scholar 

  • Pan JC, Hsiao YC (2005) Integrated inventory models with controllable lead time and backorder discount considerations. Int J Prod Econ 93:387–397

    Google Scholar 

  • Paknejad MJ, Nasri F, Affisco JF (1995) Defective units in a continuous review (s, Q) system. Int J Prod Res 33:2767–2777

    Google Scholar 

  • Park KS (1982) Inventory model with partial backorders. Int J Syst Sci 13:1313–1317

    Google Scholar 

  • Porteus LE (1985) Investing in reduced setups in the EOQ model. Manag Sci 31:998–1010

    Google Scholar 

  • Priyan S, Uthayakumar R (2014) Trade credit financing in the vendorbuyer inventory system with ordering cost reduction, transportation cost and backorder price discount when the received quantity is uncertain. J Manuf Syst 33:654–674

    Google Scholar 

  • Rosenberg D (1979) A new analysis of a lot size model with partial backlogging. Nav Res Logi Quart 26:346–353

    Google Scholar 

  • Sajadieh MS, Jokar MRA (2009) An integrated vendor–buyer cooperative model under stochastic supply lead-time. Int J Manuf Tech 41:1043–1050

    Google Scholar 

  • Sarkar B, Mandal B, Sarkar S (2015) Quality improvement and backorder price discount under controllable lead time in an inventory model. J Manuf Syst 35:26–36

    Google Scholar 

  • Sarkar B, Sarkar S (2013) An improved inventory model with partial backlogging, time varying deterioration and stock-dependent demand. Econ Model 30:924–932

    Google Scholar 

  • Wee HM, Widyadana G (2013) Single-vendor single-buyer inventory model with discrete delivery order, random machine unavailability time and lost sales. Int J Prod Econ 143:574–579

    Google Scholar 

  • Yang JS, Pan JC (2004) Just-in-time purchasing: an integrated inventory model involving deterministic variable lead time and quality improvement investment. Int J Prod Res 42:853–863

    Google Scholar 

  • Yang JQ, Zhang XM, Fu HY, Liu C (2017) Inventory competition in a dual-channel supply chain with delivery lead time consideration. Appl Math Model 42:675–692

    Google Scholar 

  • Yu AJ, Dong Y (2014) A numerical solution for a two-stage production and inventory system with random demand arrivals. Comput Oper Res 44:13–21

    Google Scholar 

  • Zhang T, Liang L, Yu Y, Yu Y (2007) An integrated vendor-managed inventory model for a two-echelon system with order cost reduction. Int J Prod Econ 109:241–253

    Google Scholar 

  • Zhou X, Shi LP, Huang BZ (2012) Integrated inventory model with stochastic lead time and controllable variability for milk runs. J Ind Manag Optim 8:657–672

    Google Scholar 

  • Zikopoulos C (2017) Remanufacturing lot sizing with stochastic lead-time resulting from stochastic quality of returns. Int J Prod Res 55(6):1565–1587

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to B. C. Giri.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Sarkar, S., Giri, B.C. A vendor–buyer integrated inventory system with variable lead time and uncertain market demand. Oper Res Int J 20, 491–515 (2020). https://doi.org/10.1007/s12351-018-0418-x

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s12351-018-0418-x

Keywords

Navigation