Simulation analysis of labor performance during overtime and impact on project duration

  • Construction Management
  • Published:
KSCE Journal of Civil Engineering Aims and scope

Abstract

The objective of this research is to quantify the anticipated impact of labor productivity during scheduled overtime on total project duration. In order to meet this objective, a Monte Carlo simulation model of variability and continuous deterioration of labor productivity during scheduled overtime of labor productivity during scheduled overtime was developed. The pattern of the productivity decline was modeled by the productivity curves reported by Business Roundtable in 1974 which is considered the most comprehensive study of construction overtime and labor productivity. Also, the techniques of statistical inference were used to fit a theoretical distribution to the productivity data obtained from CII research published in 1994. After performing the hypothesis tests, the lognormal distribution was selected to represent variability of daily labor performance during scheduled overtime in this simulation model. This research shows that estimating the impact of working overtime on the project duration without considering labor productivity decline leads to overestimation of the effectiveness of working overtime. This research also demonstrates that simulation analysis of scheduled overtime provides a more in-depth analysis of the overall impact on project schedule. The simulation analysis allows a project manager to assess and analyze the effectiveness of working different overtime options and to choose the right overtime option providing required schedule acceleration.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  • Borcherding, J. D. and Alarcon, L. F. (1991). “Quantitative effects on construction productivity.” The Construction Lawyer, Vol. 11, No. 1, pp. 1–48.

    Google Scholar 

  • Business Roundtabl. (1980). Scheduled overtime effect on construction project, A Construction Industry Cost Effectiveness Task Force Report New York, NY.

    Google Scholar 

  • CI. (1988). The effects of scheduled overtime and shift schedule on construction craft productivity, Source Document 43, Construction Industry Institute, The University of Texas at Austin.

    Google Scholar 

  • CI. (1994). Effects of scheduled overtime on labor productivity: A quantitative analysis, Source Document 98, Construction Industry Institute, The University of Texas at Austin.

    Google Scholar 

  • Halligan, D. W., Demsetz, L. A., Brown, J. D. and Pace, C. B. (1994). “Action-response model and loss of productivity in construction.” Journal of Construction Engineering and Management, Vol. 120, No. 1, DOI: 10.1061/(ASCE)07339364(1994)120:1(47).

  • Larew, R. (1995). Are any construction overtime “studies” reliable?, C&SM/C.1.1-C&SM/C.1.1.

    Google Scholar 

  • Law, A. M. and Kelton, W. D. (1991). Simulation Modeling & Analysis, New York: McGraw-Hill, Inc.

    MATH  Google Scholar 

  • Thomas, R. H. and Raynar, K. A. (1997). “Scheduled overtime and labor productivity: Quantitative analysis.” Journal of Construction Engineering and Management, Vol. 123, No. 2, 181–188., DOI: 10.1061/(ASCE)0733-9364(1997)123:2(181).

    Article  Google Scholar 

  • Thomas, R. H. (1990). Effects of scheduled overtime on labor productivity: a literature review and analysis, Source Document 60, Construction Industry Institute, The University of Texas at Austin.

    Google Scholar 

  • Thomas, R. H. and Kramer, D. F. (1988). The manual of construction productivity measurement and performance evaluation. Source Document, The Construction Industry Institute, The University of Texas at Austin.

    Google Scholar 

  • Thomas, R. H. and Mathews, C. T. (1986). An analysis of the methods for measuring construction productivity, Source Document 13, Construction Industry Institute, The University of Texas at Austin.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Sungkwon Woo.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Woo, S. Simulation analysis of labor performance during overtime and impact on project duration. KSCE J Civ Eng 20, 2614–2623 (2016). https://doi.org/10.1007/s12205-016-0956-9

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s12205-016-0956-9

Keywords

Navigation