Abstract
Schedule overrun is one of the greatest hindrances to construction project performance, thereby making schedule management an integral part of construction project management. The aim of this study is to examine how the effect of sustainable energy management (SEM) and sustainable waste management (SWM) on schedule performance (SP) is mediated by technological complexity (TC) and moderated by project size (PS). Data were obtained by means of a questionnaire survey of 168 completed construction projects in Nigeria. The partial least squares structural equation modelling (PLS-SEM) technique was adopted in analysing the collected data. The results show that TC partially mediates the relationship between SWM and SP, while TC fully mediates the relationship between SEM and SP. Also, the findings of the study indicate that the negative effect of SWM on SP will be greater with large PS. This study contributes to previous studies in the area of schedule management, by providing empirical proof to explain the means through which SWM and SEM could lead to SP through TC, and how this would vary depending on PS. The study proffers ways for contractors to improve the SP of their projects considering PS and TC.
Similar content being viewed by others
Data availability
The datasets used and/or analysed during the current study are available from the corresponding author on reasonable request.
References
Ajayi SO, Oyedele LO, Akinade OO, Bilal M, Owolabi HA, Alaka HA, Kadiri KO (2016) Reducing waste to landfill: a need for cultural change in the UK construction industry. Journal of Building Engineering 5:185–193
Al-Ghwayeen WS, Abdallah AB (2018) Green supply chain management and export performance: the mediating role of environmental performance. J Manuf Technol Manag 29(7):1233–1252
Al-Rubaye ZR, Mahjoob AMR (2020) Using measured mile method to quantify the loss of labor productivity in Iraqi construction site. Asian Journal of Civil Engineering 21(7):1287–1296
Andersson U, Cuervo-Cazurra A, Nielsen BB (2014) From the editors: explaining interaction effects within and across levels of analysis: Springer.
Arashpour M, Wakefield R, Lee E, Chan R, Hosseini MR (2016) Analysis of interacting uncertainties in on-site and off-site activities: implications for hybrid construction. Int J Project Manage 34(7):1393–1402
Baah C, Opoku-Agyeman D, Acquah ISK, Agyabeng-Mensah Y, Afum E, Faibil D, Abdoulaye FAM (2021) Examining the correlations between stakeholder pressures, green production practices, firm reputation, environmental and financial performance: evidence from manufacturing SMEs. Sustainable Production and Consumption 27:100–114
Bajjou MS, Chafi A (2020) Empirical study of schedule delay in Moroccan construction projects. Int J Constr Manag 20(7):783–800
Bakchan A, Faust KM (2019) Construction waste generation estimates of institutional building projects: leveraging waste hauling tickets. Waste Manage 87:301–312
Bakchan A, Faust KM, Leite F (2019) Seven-dimensional automated construction waste quantification and management framework: integration with project and site planning. Resour Conserv Recycl 146:462–474
Baron RM, Kenny DA (1986) The moderator–mediator variable distinction in social psychological research: conceptual, strategic, and statistical considerations. J Pers Soc Psychol 51(6):1173
Bosch-Rekveldt M, Jongkind Y, Mooi H, Bakker H, Verbraeck A (2011) Grasping project complexity in large engineering projects: the TOE (technical, organizational and environmental) framework. Int J Project Manage 29(6):728–739
Burke CM, Morley MJ (2016) On temporary organizations: a review, synthesis and research agenda. Human Relations 69(6):1235–1258
Cabrera R, González D (2019) Influences of technological attributes on sourcing of manufacturing technologies in developing countries: the case of Peru. Management Research: Journal of the Iberoamerican Academy of Management
Carvalho MM, Rabechini R Jr (2017) Can project sustainability management impact project success? An empirical study applying a contingent approach. Int J Project Manage 35(6):1120–1132
Chaichan MT, Kazem HA (2016) Energy conservation and management for houses and building in Oman-case study. Saudi Journal of Engineering and Technology 1(3):69–76
Chin WW (1998) The partial least squares approach to structural equation modeling. Modern Methods for Business Research 295(2):295–336
Chin WW, Marcolin BL, Newsted PR (2003) A partial least squares latent variable modeling approach for measuring interaction effects: results from a Monte Carlo simulation study and an electronic-mail emotion/adoption study. Inf Syst Res 14(2):189–217
Cohen J (1988) Statistical power analysis for the behaviors science.(2nd). New Jersey: Laurence Erlbaum Associates, Publishers, Hillsdale
Collins W, Parrish K, Gibson GE Jr (2017) Development of a project scope definition and assessment tool for small industrial construction projects. J Manag Eng 33(4):04017015
Dallasega P, Rauch E, Linder C (2018) Industry 4.0 as an enabler of proximity for construction supply chains: a systematic literature review. Comput Ind 99:205–225
Dawson JF (2014) Moderation in management research: What, why, when, and how. J Bus Psychol 29(1):1–19
de Souza Melaré AV, González SM, Faceli K, Casadei V (2017) Technologies and decision support systems to aid solid-waste management: a systematic review. Waste Manage 59:567–584
Denzin NK (2017) The research act: a theoretical introduction to sociological methods: Transaction publishers
Ding Z, Gong W, Li S, Wu Z (2018) System dynamics versus agent-based modeling: a review of complexity simulation in construction waste management. Sustainability 10(7):2484
Elzek Y, Gaafar H, Abdelsamie H (2021) The impact of green innovation on sustainability performance in travel agencies and hotels: the moderating role of environmental commitment. International Journal of Hospitality & Tourism Systems, 14(2)
Enshassi A, Ayash A, Mohamed S (2018) Key barriers to the implementation of energy-management strategies in building construction projects. International Journal of Building Pathology and Adaptation
Fassott G, Henseler J (2015) Formative (measurement). Wiley encyclopedia of management, 1–4
Fassott G, Henseler J, Coelho PS (2016) Testing moderating effects in PLS path models with composite variables. Ind Manag Data Syst 116(9):1887–1900
Floricel S, Michela JL, Piperca S (2016) Complexity, uncertainty-reduction strategies, and project performance. Int J Project Manage 34(7):1360–1383
Franz B, Leicht R, Molenaar K, Messner J (2017) Impact of team integration and group cohesion on project delivery performance. J Constr Eng Manag 143(1):04016088
Gao S, Low SP (2014) Lean construction management: Springer
Garg S, Rajput K (2017) Performance consequences on complexity in public-private partnerships: evidence from Indian highway projects
Habibi M, Kermanshachi S, Rouhanizadeh B (2019) Identifying and measuring engineering, procurement, and construction (EPC) key performance indicators and management strategies. Infrastructures 4(2):14
Hair JF, Hult GTM, Ringle C, Sarstedt M (2017) A primer on partial least squares structural equation modeling (PLS-SEM): Sage Publications.
Hair JF, Risher JJ, Sarstedt M, Ringle CM (2019a) When to use and how to report the results of PLS-SEM. Eur Bus Rev
Hair JF, Sarstedt M, Ringle CM (2019b) Rethinking some of the rethinking of partial least squares. European Journal of Marketing
Hair Jr JF, Hult GTM, Ringle C, Sarstedt M (2017) A primer on partial least squares structural equation modeling (PLS-SEM): Sage Publications
Harman, H. H. (1960). Modern factor analysis. Chicago: Univer: of Chicago press.
Harmathy N, Kontra J, Murgul V, Magyar Z (2017) Energy performance simulation and evaluation of various construction types for a residential building (international ODOO project). Paper presented at the Energy Management of Municipal Transportation Facilities and Transport
Hayes AF, Rockwood NJ (2017) Regression-based statistical mediation and moderation analysis in clinical research: observations, recommendations, and implementation. Behav Res Ther 98:39–57
He Q, Luo L, Hu Y, Chan AP (2015) Measuring the complexity of mega construction projects in China—a fuzzy analytic network process analysis. Int J Project Manage 33(3):549–563
Hertogh M, Westerveld E (2010) Playing with complexity. Management and organisation of large infrastructure projects
Hiranrat C, Harncharnchai A, Duangjan C (2021) Theory of planned behavior and the influence of communication self-efficacy on intention to pursue a software development career. J Inf Syst Educ 32(1):40–52
Huang B, Xing K, Pullen S (2017) Energy and carbon performance evaluation for buildings and urban precincts: review and a new modelling concept. J Clean Prod 163:24–35
Hwang B-G, Leong LP, Huh Y-K (2013) Sustainable green construction management: schedule performance and improvement. Technol Econ Dev Econ 19(sup1):S43–S57
Hwang B-G, Zhao X, Tan LLG (2015) Green building projects: schedule performance, influential factors and solutions. Engineering, Construction and Architectural Management
Hwang BG, Leong LP (2013) Comparison of schedule delay and causal factors between traditional and green construction projects. Technol Econ Dev Econ 19(2):310–330
Ivanova IA, Leydesdorff L (2015) Knowledge-generating efficiency in innovation systems: the acceleration of technological paradigm changes with increasing complexity. Technol Forecast Soc Chang 96:254–265
Jilke S (2020) Impact of technological uncertainty and technological complexity on organizational information processing capability: the moderating role of work experience. Eur J Innov Manag
Kabirifar K, Mojtahedi M, Wang C, Tam VW (2020) Construction and demolition waste management contributing factors coupled with reduce, reuse, and recycle strategies for effective waste management: a review. J Clean Prod 263:121265
Kandananond K (2017) The greenhouse gas accounting of a public organization: the case of a public university in Thailand. Energy Procedia 141:672–676
Kenny DA (2016) Moderation. Retrieved from davidakenny.net/cm/moderation.htm
Kim SY, Nguyen MV (2020) A performance evaluation framework for construction and demolition waste management: stakeholder perspectives. Engineering, Construction and Architectural Management
Klassen RD, Whybark DC (1999) The impact of environmental technologies on manufacturing performance. Acad Manag J 42(6):599–615
Kock N (2014) Advanced mediating effects tests, multi-group analyses, and measurement model assessments in PLS-based SEM. International Journal of e-Collaboration (IJeC) 10(1):1–13
Kock N (2015) Common method bias in PLS-SEM: a full collinearity assessment approach. International Journal of e-Collaboration (IJeC) 11(4):1–10
Kock N, Hadaya P (2018) Minimum sample size estimation in PLS-SEM: the inverse square root and gamma-exponential methods. Inf Syst J 28(1):227–261
Kock, N., & Lynn, G. (2012). Lateral collinearity and misleading results in variance-based SEM: an illustration and recommendations.
Kofoworola OF, Gheewala SH (2009) Estimation of construction waste generation and management in Thailand. Waste Manage 29(2):731–738
Lagos CI, Herrera RF, Alarcón LF (2019) Assessing the impacts of an IT LPS support system on schedule accomplishment in construction projects. J Constr Eng Manag 145(10):04019055
Laurent J, Leicht RM (2019) Practices for designing cross-functional teams for integrated project delivery. J Constr Eng Manag 145(3):05019001
Le-Hoai L, Dai Lee Y, Lee JY (2008) Delay and cost overruns in Vietnam large construction projects: a comparison with other selected countries. KSCE J Civ Eng 12(6):367–377
Leon H, Osman H, Georgy M, Elsaid M (2018) System dynamics approach for forecasting performance of construction projects. J Manag Eng 34(1):04017049
Li F, Chen J, Ying Y (2019) Innovation search scope, technological complexity, and environmental turbulence: a NK simulation. Sustainability 11(16):4279
Li Y, Lu Y, Kwak YH, Dong S (2015) Developing a city-level multi-project management information system for Chinese urbanization. Int J Project Manage 33(3):510–527
Liu H, Lin B (2017) Energy substitution, efficiency, and the effects of carbon taxation: evidence from China’s building construction industry. J Clean Prod 141:1134–1144
Lu W, Webster C, Chen K, Zhang X, Chen X (2017) Computational building information modelling for construction waste management: moving from rhetoric to reality. Renew Sustain Energy Rev 68:587–595
Luo L, He Q, Xie J, Yang D, Wu G (2016) Investigating the relationship between project complexity and success in complex construction projects. J Manag Eng 33(2):04016036
Macedo M, Galo J, De Almeida L, Lima A, d. C. (2015) Demand side management using artificial neural networks in a smart grid environment. Renew Sustain Energy Rev 41:128–133
Maistry N, McKay TM (2016) Promoting energy efficiency in a South African university. Journal of Energy in Southern Africa 27(3):1–10
Mak TM, Iris K, Wang L, Hsu S-C, Tsang DC, Li C, ..., Poon CS (2019) Extended theory of planned behaviour for promoting construction waste recycling in Hong Kong. Waste Manag 83:161-170.
Meeampol, S., & Ogunlan, S. (2006). Factors affecting cost and time performance on highway construction projects: evidence from Thailand. Journal of Financial Management of Property and Construction.
Memon AH, Zin RM (2010) Resource-driven scheduling implementation in Malaysian construction industry. International Journal of Sustainable Construction Engineering and Technology 1(2):77–90
Memon M, Cheah J, Ramayah T, Ting H, Chuah F (2019) Moderation analysis: issues and guidelines. Journal of Applied Structural Equation Modeling 3(1):1–12
Mewes, L., & Broekel, T. (2020). Technological complexity and economic growth of regions. Research Policy, 104156.
Mills, G. E., & Gay, L. R. (2016). Educational research: competencies for analysis and applications: Pearson Upper Saddle Ridge, NJ.
Molina-Solana M, Ros M, Ruiz MD, Gómez-Romero J, Martín-Bautista MJ (2017) Data science for building energy management: a review. Renew Sustain Energy Rev 70:598–609
Nguyen AT, Nguyen LD, Le-Hoai L, Dang CN (2015) Quantifying the complexity of transportation projects using the fuzzy analytic hierarchy process. Int J Project Manage 33(6):1364–1376
Nguyen LD, Le-Hoai L, Tran DQ, Dang CN, Nguyen CV (2019) Effect of project complexity on cost and schedule performance in transportation projects. Constr Manag Econ 37(7):384–399
Nigeria Federal Ministry of Power Works and Housing. (2017). Building energy efficiency guideline for Nigeria. Abuja, Nigeria.: Federal Ministry of Power, Works and Housing.
Nunayon, S. S., Olanipekun, E. A., & Famakin, I. O. (2020). Determining key drivers of efficient electricity management practices in public universities in Southwestern Nigeria. International Journal of Sustainability in Higher Education.
Ogundari IO, Otuyemi FA (2019) Project planning and monitoring analysis for sustainable environment and power infrastructure project development in Lagos State, Nigeria. Int J Crit Infrastruct 15(1):24–45
Onubi HO, Yusof NA, Hassan AS (2019) Green-site practices and environmental performance: how project complexity moderates the relationship. Construction Economics and Building 19(1):75–95
Onubi HO, Yusof NA, Hassan AS (2020a) The moderating effect of client types on the relationship between green construction practices and health and safety performance. Int J Sust Dev World 27(8):732–748
Onubi, H. O., Yusof, N. A., & Hassan, A. S. (2020b). Understanding the mechanism through which adoption of green construction site practices impacts economic performance. Journal of Cleaner Production, 254, 120170.
Onubi, H. O., Yusof, N. A., Hassan, A. S., & Bahdad, A. A. S. (2021). Forecasting the schedule performance resulting from the adoption of social distancing in construction projects. Engineering, Construction and Architectural Management.
Osmani M (2012) Construction waste minimization in the UK: current pressures for change and approaches. Procedia Soc Behav Sci 40:37–40
Paraskevopoulou C, Boutsis G (2020) Cost overruns in tunnelling projects: investigating the impact of geological and geotechnical uncertainty using case studies. Infrastructures 5(9):73
PMI P (2013) PMI's pulse of the profession in-depth report: navigating complexity. Newtown Square, PA
Podsakoff PM, MacKenzie SB, Lee J-Y, Podsakoff NP (2003) Common method biases in behavioral research: a critical review of the literature and recommended remedies. J Appl Psychol 88(5):879
Podsakoff PM, MacKenzie SB, Podsakoff NP (2012) Sources of method bias in social science research and recommendations on how to control it. Annu Rev Psychol 63:539–569
Puddicombe MS (2012) Novelty and technical complexity: critical constructs in capital projects. J Constr Eng Manag 138(5):613–620
Ramayah T, Cheah J, Chuah F, Ting H, Memon MA (2018). Partial least squares structural equation modelling (PLS-SEM) using SmartPLS 3.0: an updated and practical guide to statistical analysis (2nd Edition ed.): Pearson Malaysia Sdn Bhd
Razali NM, Wah YB (2011) Power comparisons of Shapiro-Wilk, Kolmogorov-Smirnov, Lilliefors and Anderson-Darling tests. Journal of Statistical Modeling and Analytics 2(1):21–33
Rogers EM, Shoemaker FF (1971) Communication of Innovations; a cross-cultural approach
Rungtusanatham M, Miller J, Boyer K (2014) Theorizing, testing, and concluding for mediation in SCM research: tutorial and procedural recommendations. J Oper Manag 32(3):99–113
Sarstedt M, Ringle CM, Hair JF (2017) Partial least squares structural equation modeling. Handbook of Market Research 26(1):1–40
Schneider CQ, Wagemann C (2012) Set-theoretic methods for the social sciences: a guide to qualitative comparative analysis. Cambridge University Press, Cambridge
Sebi C, Vernay A-L (2020) Community renewable energy in France: the state of development and the way forward. Energy Policy 147:111874
Shalwani A, Lines BC (2020) An empirical analysis of the causes of cost and schedule growth for small healthcare and educational construction projects. Int J Construct Educ Res 1–20
Shehu Z, Endut IR, Akintoye A, Holt GD (2014) Cost overrun in the Malaysian construction industry projects: a deeper insight. Int J Project Manage 32(8):1471–1480
Shi, Q., Hertogh, M., Bosch-Rekveldt, M., Zhu, J., & Sheng, Z. (2020). Exploring decision-making complexity in major infrastructure projects: a case study from China. Project Management Journal, 8756972820919205.
Shrestha B, Shrestha PP, Maharjan R, Gransberg D (2022) Cost, change order, and schedule performance of highway projects. J Leg Aff Disput Resolut Eng Constr 14(1):04521044
Shrestha PP, Fathi M (2019) Impacts of change orders on cost and schedule performance and the correlation with project size of DB building projects. J Leg Aff Disput Resolut Eng Constr 11(3):04519010
Sinesilassie, E. G., Tabish, S. Z. S., & Jha, K. N. (2017a). Critical factors affecting schedule performance. Engineering, Construction and Architectural Management.
Sinesilassie, E. G., Tabish, S. Z. S., & Jha, K. N. (2017b). Critical factors affecting schedule performance: a case of Ethiopian public construction projects–engineers’ perspective. Engineering, Construction and Architectural Management.
Sola, A. V., & Mota, C. M. (2020). Influencing factors on energy management in industries. Journal of Cleaner Production, 248, 119263.
Sorrell, S., Mallett, A., & Nye, S. (2011). Barriers to industrial energy efficiency: a literature review.
Trinh MT, Feng Y (2020) Impact of project complexity on construction safety performance: moderating role of resilient safety culture. J Constr Eng Manag 146(2):04019103
Umeokafor N, Windapo A, Evangelinos K (2019) Causal inferences of external–contextual domains on complex construction, safety, health and environment regulation. Saf Sci 118:379–388
Vidal, L. A., & Marle, F. (2008). Understanding project complexity: implications on project management. Kybernetes.
Vieira CS, Pereira PM (2015) Use of recycled construction and demolition materials in geotechnical applications: a review. Resour Conserv Recycl 103:192–204
Wang J, Yu B, Tam VW, Li J, Xu X (2019) Critical factors affecting willingness of design units towards construction waste minimization: an empirical study in Shenzhen, China. J Clean Prod 221:526–535
Wang, L., Morabito, M., Payne, C. T., & Robinson, G. (2020). Identifying institutional barriers and policy implications for sustainable energy technology adoption among large organizations in California. Energy Policy, 146, 111768.
Xia, B., & Chan, A. P. (2012). Measuring complexity for building projects: a Delphi study. Engineering, Construction and Architectural Management.
Yang T, Zhao L, Li W, Zomaya AY (2020) Reinforcement learning in sustainable energy and electric systems: a survey. Annu Rev Control 49:145–163
Yayavaram S, Chen WR (2015) Changes in firm knowledge couplings and firm innovation performance: the moderating role of technological complexity. Strateg Manag J 36(3):377–396
Yusof NA, Tabassi AA, Kamal EM (2020) Do environmental, economic and reputational advantages strengthen green practices’ impact on environmental performance? Corp Soc Responsib Environ Manag 27(5):2081–2093
Zarei B, Sharifi H, Chaghouee Y (2018) Delay causes analysis in complex construction projects: a semantic network analysis approach. Prod Plan Control 29(1):29–40
Author information
Authors and Affiliations
Contributions
All the authors contributed to the study conception and design. Data collection and analysis were performed by HOO, NY, AASB, and ASH. The first draft of the manuscript was written by HOO, and all the authors commented on previous versions of the manuscript. All the authors read and approved the final manuscript.
Corresponding author
Ethics declarations
Ethics approval and consent to participate
This study involved human participants. Ethics approval was granted by the Ethics Committee for Research involving Human Subjects, Universiti Sains Malaysia (JEPeMUSM), with study protocol code USM/JEPeM/18090438 on 9 May 2019.
Consent for publication
Not applicable.
Competing interests
The authors declare no competing interests.
Additional information
Responsible Editor: Philippe Garrigues
Publisher's note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
About this article
Cite this article
Onubi, H.O., Yusof, N., Hassan, A.S. et al. Effect of energy management and waste management on schedule performance: role of technological complexity and project size. Environ Sci Pollut Res 29, 29075–29090 (2022). https://doi.org/10.1007/s11356-021-18376-4
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s11356-021-18376-4