The work done on the test site to ensure the operational safety of the powerhouse of the Zagorsk PSP-2 after its leveling is described. The controlled compensation grouting technology for leveling the powerhouse of the Zagorsk PSP-2 is substantiated.
Similar content being viewed by others
References
A. V. Aleksandrov, E. N. Bellendir, S. Ya. Lashchenov, and R. Sh. Al’zhanov, “Remediation of the consequences of the subsidence of the Zagorsk PSPP-2 powerhouse,” Gidrotekhn. Stroit., No. 6, 81 – 89 (2016).
M. G. Zertsalov, A. N. Simutin, and V. V. Aleksandrov, “Compensation grouting technology for protection of buildings and other structures,” Vestn. MGSU, No. 6, 32 – 40 (2015).
E. N. Bellendir, V. V. Aleksandrov,M. G. Zertsalov, and A. N. Simutin, “Building and structure protection and leveling using compensation grouting technology,” Power Technol. Eng., 50(2), 142 – 146 (2016).
A. V. Aleksandrov, E. N. Bellendir, P. A. Vaver, and A. N. Simutin, “Experimental substantiation of leveling the Zagorsk PSP-2 powerhouse,” Power Technol. Eng., 52(5), 517 – 524 (2019).
A. Bezuijen, Compensation Grouting in Sand. Experiments, Field Experiences and Mechanisms (2010), ISBN 978-90-8570-507-9.
Clief Kettle, Compensation Grouting-Evolution, Field and Application and Current State of the Art in UK Practice.
H. Knitsch, “Visualization of relevant data for compensation grouting,” Tunnel, No. 3, 38 – 45 (2008).
Author information
Authors and Affiliations
Corresponding author
Additional information
Translated from Gidrotekhnicheskoe Stroitel’svo, No. 5, May 2021, pp. 8 – 13. DOI: 10.34831/EP.2021.49.61.001
Rights and permissions
About this article
Cite this article
Aleksandrov, A.V. Operational Safety of the Zagorsk PSP After Leveling of Its Powerhouse. Power Technol Eng 55, 477–481 (2021). https://doi.org/10.1007/s10749-021-01384-2