Abstract
Knowing accurate values of rock engineering parameters in hard rock condition is the key in estimating and adjusting TBM performance. In this study, TBM penetration per revolution (Pr) as driving parameter, TBM operational parameters including cutterhead torque (Tq), field penetration index (FPI), thrust force (Th), cutter load (Fn), cutterhead rotational speed revolution per minute (RPM), and also cutterhead diameter as a mechanical machine specification are used to predict geomechanical parameters including rock quality designation (RQD) and unconfined compressive strength (UCS) based on reverse analysis in three types of strong rocks (Tuff, Andesite, Diorite) along the Southern lot of Kerman water transfer tunnel; KrWCT. A soft computing method called least squares-support vector machine (Ls-SVM), is trained using operating and driving data as well as rock engineering parameters gathered from the KrWCT project which is excavated in hard rock condition using double shield TBM. Due to the lack of access to the excavation face in mechanized tunneling, the collection of geomechanical data on the rock mass is possible only through the examination of excavated material and limited inspections during cutterhead repairs. Therefore, this paper has tried to predict and classify the rock engineering factors using some indicators related to machine performance, mechanical specification, and TBM operational parameters. Among the data collected during the pre-construction and construction phases of the project, the dataset was classified into 42 zones, and the reasonable distribution intervals of the main tunneling factors corresponding to each zone were defined. New empirical equations are developed to estimate the properties of igneous rocks based on linear and non-linear multivariable regression (MR). Several loss functions were used to assess the performance and precision of the applied methods. The results of the proposed models indicate an acceptable and reliable accuracy.
Highlights
-
TBM data predicts rock engineering properties in complex geological condition.
-
Forecasting RQD and UCS in deep tunnels through strong rocks using reverse analysis.
-
Developing empirical models for calculating UCS and RQD based on statistical analysis.
-
Detailed analysis of Ls-SVM supervised network for rock geomechanical prediction.
-
Examining model accuracy with various statistical indices and loss functions.
Similar content being viewed by others
References
Barton N (2000) TBM tunnelling in jointed and faulted rock. ISBN 9789058093417. 184 p
Benardos A, Kaliampakos DC (2004) Modelling TBM performance with artificial neural networks. Tunnel under Space Tech 19:597–605. https://doi.org/10.1016/j.tust.2004.02.128
Benato A, Oreste P (2015) Prediction of penetration per revolution in TBM tunneling as a function of intact rock and rock mass characteristics. Inter J Rock Mech Min Sci 74:119–127. https://doi.org/10.1016/j.ijrmms.2014.12.007
Bieniawski ZT, Celada B, Galera JM (2007) TBM excavability: prediction and machine-rock interaction. Rapid Excav Tunnel Conf. 1118–1130.
Bruland, A., 1998. Hard rock tunnel boring. PhD Thesis, Norwegian University of Science and Technology.
Cassinelli F, Cina S, Innaurato N, Mancini R, Sampaolo A (1982) Power consumption and metal wear in tunnel-boring machines: analysis of tunnel boring machine operation in hard rock. Inter J Rock Mech Min Sci Geomech Abst 82:73–81. https://doi.org/10.1016/0148-9062(83)91823-5
Chen C, Seo H (2023) Prediction of rock mass class ahead of TBM excavation face by ML and DL algorithms with Bayesian TPE optimization and SHAP feature analysis. Acta Geotech. https://doi.org/10.1007/s11440-022-01779-z
Dullmann J (2014) Performance optimization and wear forecast in hydro-shield tunneling in soft ground. PhD Thesis, Ruhr University.
Elhaik E (2022) Principal component analyses (PCA)-based findings in population genetic studies are highly biased and must be reevaluated. Sci Rep. https://doi.org/10.1038/s41598-022-14395-4
Farrokh E, Rostami J (2009) Effect of adverse geological condition on TBM operation in Ghomroud tunnel conveyance project. Tunnel under Space Tech 24(4):436–446. https://doi.org/10.1016/j.tust.2008.12.006
Farrokh E, Rostami J, Laughton C (2010) Study of various models for estimation of penetration rate of hard rock TBMs. Tunnel under Space Tech 30:110–123. https://doi.org/10.1016/j.tust.2012.02.012
Festa D, Broere W, Bosch JW (2012) An investigation into the forces acting on a TBM during driving –Mining the TBM logged data. Tunnel under Space Tech 32:143–157. https://doi.org/10.1016/j.tust.2012.06.006
Gao X, Shi M, Song X, Zhang C, Zhang H (2020) Recurrent neural networks for real-time prediction of TBM operating parameters. Auto Const 98:225–235. https://doi.org/10.1016/j.autcon.2018.11.013
Gong QM, Zhao J (2007) Influence of rock brittleness on TBM penetration rate in Singapore granite. Tunnel under Space Tech 22(3):317–324. https://doi.org/10.1016/j.tust.2006.07.004
Gong QM, Zhao J (2009) Development of a rock mass characteristics model for TBM penetration rate prediction. Inter J Rock Mech Min Sci 46(1):8–18. https://doi.org/10.1016/j.ijrmms.2008.03.003
Grima MA, Bruines PA, Verhoef PNW (2000) Modeling tunnel boring machine performance by Neuro-Fuzzy methods. Tunnel under Space Tech 15(3):259–269. https://doi.org/10.1016/S0886-7798(00)00055-9
Hassanpour J, Rostami J, Khamehchiyan M, Bruland A, Tavakoli HR (2010) TBM performance analysis in pyroclastic rocks, a case history of Karaj water conveyance tunnel (KWCT). Rock Mech Rock Eng 43:427–445. https://doi.org/10.1007/s00603-009-0060-2
Hassanpour J, Rostami J, Zhao J (2011) A new hard rock TBM performance prediction model for project planning. Tunnel under Space Tech 29:595–603. https://doi.org/10.1016/j.tust.2011.04.004
Hassanpour J, Rostami J, Zhao J, Tarigh Azali S (2015) TBM performance and disc cutter wear prediction based on ten years’ experience of TBM tunnelling in Iran. Geomech Tunnel 8(3):239–247
Hassanpour J, Ghaedi Vanani AA, Rostami J, Cheshomi A (2016) Evaluation of common TBM performance prediction models based on field data from the second lot of Zagros water conveyance tunnel (ZWCT2). Tunnel under Space Tech 52:147–156. https://doi.org/10.1016/j.tust.2015.12.006
Hassanpour J, Esmaeili Vardanjani S, Rostami J, Cheshomi A (2019) Engineering geological studies used for redesigning and employing a hard rock TBM in soft rock formations of Chamshir water conveyance tunnel. Geopersia 9(1):1–20
He M, Ribeiro e Sousa L, Miranda T, Zhu G (2015) Rock burst laboratory tests database-application of data mining techniques. Eng Geo 185:116–130. https://doi.org/10.1016/j.enggeo.2014.12.008
Jolliffe LT, Cadima J (2016) Principal component analysis: a review and recent developments. Philos Trans Royal Soci a: Math Phy Eng Sci. https://doi.org/10.1098/rsta.2015.0202
Jung JH, Chung H, Kwon YS, Lee IM (2019) An ANN to predict ground condition ahead of tunnel face using TBM operational data. KSCE J Civi Eng 23:3200–3206. https://doi.org/10.1007/s12205-019-1460-9
Junzhou H, Guopeng J, Bin L, Shiwu N, Junbo L, Hanyang W (2022) Advance prediction method for rock mass stability of tunnel boring based on deep neural network of time series. Proc Inst Mech Eng Part C: J Mech Eng Sci 236:10. https://doi.org/10.1177/09544062211061682
Khatti J, Samadi H, Grover KS (2023) Estimation of settlement of pile group in clay using soft computing techniques. Geotech Geology Eng. https://doi.org/10.1007/s10706-023-02643-x
Liu Q, Huang X, Gong Q, Du L, Pan Y, Liu J (2016) Application and development of hard rock TBM and its prospect in China. Tunnel under Space Tech 57:33–46. https://doi.org/10.1016/j.tust.2016.01.034
Liu B, Wang R, Guan Z, Li J, Xu Z, Guo X, Wang Y (2019) Improved support vector regression models for predicting rock mass parameters using tunnel boring machine operational data. Auto Const. https://doi.org/10.1016/j.tust.2019.04.014
Liu B, Wang R, Zhao G, Guo X (2020a) Prediction of rock mass parameters in the TBM tunnel based on BP neural network integrated simulated annealing algorithm. Tunnel under Space Tech. https://doi.org/10.1016/j.tust.2019.103103
Liu Q, Wang X, Huang X, Yin X (2020b) Prediction model of rock mass class using classification and regression tree integrated AdaBoost algorithm based on TBM driving data. Tunnel under Space Tech 106:103595. https://doi.org/10.1016/j.tust.2020.103595
Mahmoodzadeh M, Taghizadeh M, Mohammed AH, Ibrahim HH, Samadi H, Mohammadi M, Rashidi S (2022) Tunnel wall convergence prediction using optimized LSTM deep neural network. Geomech Eng 31(6):545–556. https://doi.org/10.12989/gae.2022.31.6.545
Manafiazar A, Khamehchiyan M, Nadiri AA, Sharifikia M (2023) Learning simple additive weighting parameters for subsidence vulnerability indices in Tehran plain (Iran) by artificial intelligence methods. Eur J Envi Civil Eng. https://doi.org/10.1080/19648189.2023.2205914
Michael JR (1983) The stabilized probability plot. Biometrika 70(1):11–17
Pourhashemi SM, Ahangari K, Hassanpour J, Eftrekhari SM (2022) TBM performance analysis in very strong and massive rocks; case study: Kerman water conveyance tunnel project. Iran Geomech Geoeng an Inter J 17(4):1110–1122. https://doi.org/10.1080/17486025.2021.1912410
Rostami J (2008) Hard rock TBM cutterhead modeling for design and performance prediction. Geomech Tunnel (aust J Geotech Eng) 1:18–28. https://doi.org/10.1002/geot.200800002
Rostami J (2016) Performance prediction of hard rock tunnel boring machines (TBMs) in difficult ground. Tunnel under Space Tech 57:173–182. https://doi.org/10.1016/j.tust.2016.01.009
Samadi H, Hassanpour J (2022) Developing the empirical models for predicting the EPB operating parameters in strong Limestone. Iranian J Eng Geol 15(1)
Samadi H, Hassanpour J, Farrokh E (2021) Maximum surface settlement prediction in EPB TBM tunneling using soft computing techniques. In J Phys: Conf Ser 1973(1):012195. https://doi.org/10.1088/1742-6596/1973/1/012195
Samadi H, Hassanpour J, Tarigh Azali S (2022) Developing GEP technique for prediction of EPB-TBM performance in limestone strata. TBMDigs 2022. Austria, 158–164.
Samadi H, Hassanpour J, Rostami J (2023a) Prediction of earth pressure balance for EPB-TBM using machine learning algorithms. Inter J Geo-Eng 14(1):21. https://doi.org/10.1186/s40703-023-00198-7
Samadi H, Mahmoodzadeh A, Hussein Mohammed A, Alenizi FA, Hashim Ibrahim H, Nematollahi M, Babeker Elhag A (2023b) Application of several fuzzy-based techniques for estimating tunnel boring machine performance in metamorphic rocks. Rock Mech Rock Eng. https://doi.org/10.1007/s00603-023-03602-x
Sapigni M, Berti M, Behtaz E, Busillo A, Cardone G (2002) TBM performance estimation using rock mass classification. Inter J Rock Mech Min Sci 39:771–788. https://doi.org/10.1016/S1365-1609(02)00069-
Shorack GR, Wellner JA (1986) Empirical processes with applications to statistics. Wiley. ISBN 0-471-86725-X, 248–250.
SOI Company (2016) Engineering geological report of Kerman water conveyance tunnel. Unpublished.
Suykens JAK, Vandewalle J (1999) Least squares support vector machine classifiers. Neur Proc Let 9(3):293–300. https://doi.org/10.1023/A:1018628609742
Wu ZJ, Zhang PL, Fan LF, Liu QS (2019) Numerical study of the effect of confining pressure on the rock breakage efficiency and fragment size distribution of a TBM cutter using a coupled FEM-DEM method. Tunnel under Space Tech 88:260–275. https://doi.org/10.1016/j.tust.2019.03.012
Wu Z, Wei R, Chu Z, Liu Q (2021) Real-time rock mass condition prediction with TBM tunneling big data using a novel rock–machine mutual feedback perception method. J Rock Mech Geotech Eng 13(6):1311–1325. https://doi.org/10.1016/j.jrmge.2021.07.012
Yagiz S (2008) Utilizing rock mass properties for predicting TBM performance in hard rock condition. Tunnel under Space Tech 23(3):326–339. https://doi.org/10.1016/j.tust.2007.04.011
Yagiz S (2017) New equations for predicting the field penetration index of tunnel boring machines in fractured rock mass. Arab J Geosci. https://doi.org/10.1007/s12517-016-2811-1
Yagiz S, Gokceoglu C (2010) Application of fuzzy inference system and nonlinear regression models for predicting rock brittleness. Exp Sys App 37(3):2265–2272. https://doi.org/10.1016/j.eswa.2009.07.046
Yagiz S, Karahan H (2011) Prediction of hard rock TBM penetration rate using particle swarm optimization. Inter J Rock Mech Min Sci 48:427–433. https://doi.org/10.1016/j.ijrmms.2011.02.013
Yagiz S, Karahan H (2015) Application of various optimization techniques and comparison of their performances for predicting TBM penetration rate in rock mass. Inter J Rock Mech Min Sci 80:308–315. https://doi.org/10.1016/j.ijrmms.2015.09.019
Yamamoto T, Shirasagi S, Yamamoto S, Mito Y, Aoki K (2003) Evaluation of the geological condition ahead of the tunnel face by geo-statistical techniques using TBM operational data. Tunnel under Space Tech 18(2):213–221. https://doi.org/10.1016/S0886-7798(03)00030-0
Yang H, Song K, Zhou J (2022) Automated recognition model of geomechanical information based on operational data of tunneling boring machines. Rock Mech Rock Eng 55:1499–1516. https://doi.org/10.1007/s00603-021-02723-5
Zheng YL, Zhang QB, Zhao J (2016) Challenges and opportunities of using tunnel boring machines in mining. Tunnel under Space Tech 57:287–299. https://doi.org/10.1016/j.tust.2016.01.023
Zhou C, Ding L, Zhou Y, Zhang H, Skibniewski MJ (2019) Hybrid support vector machine optimization model for prediction of energy consumption of cutter head drives in shield tunneling. J Comput Civi Eng. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000833
Zhu H, Wang X, Chen X, Zhang L (2020) Similarity search and performance prediction of shield tunnels in operation through time series data mining. Automat Const 114:103178. https://doi.org/10.1016/j.autcon.2020.103178
Funding
No external funding was used.
Author information
Authors and Affiliations
Corresponding author
Ethics declarations
Conflict of Interest
The authors proclaim that they have no known contending financial interests or personal relationships that could have appeared to influence the work reported in this paper.
Additional information
Publisher's Note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
Springer Nature or its licensor (e.g. a society or other partner) holds exclusive rights to this article under a publishing agreement with the author(s) or other rightsholder(s); author self-archiving of the accepted manuscript version of this article is solely governed by the terms of such publishing agreement and applicable law.
About this article
Cite this article
Samadi, H., Karimi, H., Khamehchiyan, M. et al. Prediction of Engineering Characteristics of Rock Masses Using Actual TBM Performance Data with Supervised and Unsupervised Learning Algorithms (a Case Study in Strong to Very Strong Igneous and Pyroclastic Rocks). Rock Mech Rock Eng (2024). https://doi.org/10.1007/s00603-024-03903-9
Received:
Accepted:
Published: