Synonyms

DAG scheduling; Workflow scheduling

Definition

Task Graph Scheduling is the activity that consists in mapping a task graph onto a target platform. The task graph represents the application: Nodes denote computational tasks, and edges model precedence constraints between tasks. For each task, an assignment (choose the processor that will execute the task) and a schedule (decide when to start the execution) are determined. The goal is to obtain an efficient execution of the application, which translates into optimizing some objective function, most usually the total execution time.

Discussion

Introduction

Task Graph Scheduling is the activity that consists in mapping a task graph onto a target platform. The task graph is given as input to the scheduler. Hence, scheduling algorithms are completely independent of models and methods used to derive task graphs. However, it is insightful to start with a discussion on how these task graphs are constructed.